Tag Archives: Microsoft Project 2010

Slack (or Float) types in Microsoft Project 2013, Part 2

  Hi, Let us continue with Slack story in MS PROJECT 2013. First I will create a new Project with Task List: Because picture is too big I will show you the Gant Chart: Now, again I will apply the … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , , , | 1 Comment

How to get percentage of costs in MS PROJECT 2010 or 2013!

  Hi, my Blog reader have a problem! He want to know how much money did he spend and, he wants that in percentage of Baseline in MS PROJECT 2010. He had sent me his mpp file! Here it is: … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PRoject Management | Tagged , , , | 4 Comments

Network diagram and diagonal lines in MS PROJECT 2010, and 2013!

  I have one question from my Blog Post reader, about Network Diagram in MS PROJECT 2010: “Hi! I´m from Argentina and I was reading your blog, It´s really interesting and was really helpful for me. Thanks very much! I … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI | Tagged , , | 1 Comment

How to get the right name for a PROJECT SUBPROJECT in MS PROJECT?

  Hi, again, one question from my Blog Reader: “Please assist. When I insert a subproject (Title: Primary Heat Exchanger) into my Master Schedule, it inserts the project but doesn’t give it the same saved name in the Master Schedule. … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, PMI, PRoject Management | Tagged , , | 4 Comments

Units and Peak Units in MS PROJECT 2010! What are they?

Hi, I got this comment from one of my Blog readers: “I’ve seen there is a bug on calculation of USE!there are 2 conditions of fault: a) fixed work,,, you change duration… nothing happens to resource % useb) fixed Duration … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI | Tagged , , | Leave a comment

Finish date and the problem in MS PROJECT 2010! Or not?

Hi guys, I have a question from one of my Blog readers: “Is it possible to see Finish Variance in working days instead of calendar days? e.g. If i completed my task on Monday, instead of Friday, i want to … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PRoject Management | Tagged , , | 1 Comment

How to Create and publish new Project from MS PROJECT 2010 to MS PROJECT SERVER 2010

  Hi, let me show you hot to create a brand new Project in MS PROJECT PROFESSIONAL 2010, and then hot to Publish it into MS PROJECT SERVER 2010! First I will open MS PROJECT PROFESSIONAL 2010 and I will … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project Server 2010 | Tagged , | 6 Comments

How to avoid duplicated Resources in Project with Subprojects in MS PROJECT 2013?

Hi, one of my Blog readers had a problem! He made a Project with Resource, and Subprojects with same resources, and then those Resources were duplicated. I will use MS PROJECT 2013, but it works in MS PROJECT 2010 in … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013 | Tagged , | 13 Comments

Tracking in MS PROJECT SERVER 2010–Defining Time Reporting Periods

  Hi, if you decide to track the Task progress via MS PROJECT SERVER 2010 timesheet than you have to define Time Reporting Periods. To do that go to Server Settings and then Time Reporting Periods:         … Continue reading →

Posted in Uncategorized | Tagged , , , | Leave a comment

Tracking in MS PROJECT SERVER 2010–Defining Fiscal Periods

  Hi, Every Project has to be tracked. In Microsoft Project Server 2010 you can choose between two approaches: Effort-based: You are collecting time spending on Tasks, or during some period of time Duration-based: You are collecting percent of complete … Continue reading →

Posted in Uncategorized | Tagged , , , , | 1 Comment