How to hold Total Hours of work per Task when Actual Work is less then estimated hours in MS PROJECT 2016?
Hi, Today I’m going to explain how to solve a problem which one of my Blog Readers have in MS PROJECT 2016. Let us say that we have a Project with Task which is 6 weeks long. For this Task … Continue reading
How to change multiple Resources on Tasks in progress with MS PROJECT 2016?
Hi, today I will show you how to change multiple Resources when you have Tasks in progress with Microsoft Project 2016! Firs I’m going to create brand new Project with two simple Tasks: Now suppose that I have those Resources … Continue reading
The Agile field in Microsoft Project online
Hi, In Microsoft Project Online, there is a new Field – Agile! I will show you what can you (or can’t) do with it! First I will create brand new Waterfall Project: and I will get: As you can see, … Continue reading
Microsoft Project 2016 and Kanban!
Hi, in my previous post I wrote about Microsoft Project 2016 and Scrum. Now, I will show you some other things, based on Kanban Agile methodology. This post will be much shorter than previous one, because you can use everything … Continue reading
Microsoft Project 2016 and SCRUM
Hi, as I promised, today I will cover Scrum with MS PROJECT 2016! But, first of all what do we need form Scrum (I will talk what we need – by the book)? We need: Product Backlog and Sprint Backlog. … Continue reading
Microsoft Project 2016 goes Agile! YEAH!
Ladies and Gentleman, all Project users, as you know Microsoft Project was intended for all kind of Projects, but let’s be honest, it wad made only for Waterfall Projects. From now on, that is history. Microsoft Project goes Agile – … Continue reading
Additional Resources assigning to the Task which have work in progress in MS PROJECT 2016
Hi, Today I’m going to explain what happens if I assign additional resource in Task which has a progress with MS PROJECT 2016. First, I’m going to create brand new Project: I have two resources available: I will assign John … Continue reading
Overtime Work and Fixed Duration in MS PROJECT 2016!
Hi, today I’m going to show relation between Fixed Duration Task Type, and Overtime Work in MS PROJECT 2016. First I’m going to create a simple Project with one Task – Fixed Duration: As you can see In the Gant … Continue reading
Overtime work at specific day–is it possible in MS PROJECT 2016?
Hi, In this post, I will show you answer to one of my blog readers. He asked me is it possible to put Overtime Work at specific day in MS PROJECT 2016? Let’ say that we have a simple Project, … Continue reading
Inactive Tasks and Actuals in MS PROJECT 2016
Hi, I saw very interesting discussion in LinkedIn, about making Task Inactive if it has actuals. First let me show the “issue”. I will create brand new Project in MS PROJECT 2016: and I will create John as Resource with … Continue reading