Author Archives: Nenad Trajkovski

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!

Milestone and Finish to Finish relationship in MS PROJECT 2016

Hi, I’ve got an interesting question form one of my blog reader. He’s got a problem. I will show you what kind of Problem does he has with MS PROJECT 2016! Firs I will create new Project: Everything looks perfect. … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Is it possible to make a Project plan without Project Start Date in MS Project 2016!

  Hi, I’ve got very interesting question from one of my blog readers: “Is it possible to create project plan without Start date, and the let MS PROJECT 2016 to calculate finish like t0 + ndays?” I will show you … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 1 Comment

Task type and Resource Calendars in MS PROJECT 2016

Hi, I’ve got very specific question from one of my blog Reader, and I’m going to answer this step by step using MS PROJECT 2016 Here is Scenario from my Blog Reader (Italic font represent his questions, and Normal font represent … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Importing Resources from Excel into MS PROJECT 2013 and PROJECT 2016–VIDEO IS HERE!

I’m proudly announce that Webucator (www.webucator.com) recorder the Video https://www.youtube.com/watch?v=mniDdkKxgpM&feature=youtu.be of my Blog Post which you  can Find here: https://ntrajkovski.com/2015/02/27/importing-resources-from-excel-into-ms-project-2013/. If you want learn a lot about MS PROJECT, I strongly recommend that you visit their site https://www.webucator.com/microsoft-training/project.cfm, and you … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2016 | Tagged , | Leave a comment

Resource calendar vs. Task Calendar, and weekends in MDS PROJECT 2016

Hi, Again, I have a question from one of my Blog readers, which is related to my previous post: “Hi Nenad,¸ Thank you very mush. But can you please explain the following inconsistency in MSP behavior: If in the example … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , | 4 Comments

Resource Calendar and weekend!

  Hi, Again, I have a question from one of my Blog readers: “Nenad, I’m new to MS Project and really appreciate information on this site. I have a question regarding your post “Resource vs. Task Calendar in MS PROJECT … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , | 2 Comments

Task 0 in MS PROJECT 2016

  Hi, This post will be short, but very useful. I have a question from one of my Blog Readers: “Hi Nenad,I discovered hat my task number usually starts from 1 instead of 0.Kindly assist on this.” I will show … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged | 4 Comments

Work assigned to Tasks vs. Work assigned to resources and Task Types in MS PROJECT 2016

Hi. Today I will show you what happens when you put work in hours to the Tasks, and then assign Resources to the Task, using MS PROJECT 2016. Firs II ‘m going to create new Project: As you can see, … Continue reading

Posted in Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged | 2 Comments

Duration, Work and Units relation with no Resources assigned

Hi, I have a question from my Blog Reader: “If you are not using resources in the scheduling, should you always just leave the Effort Driven box unchecked?” I will answer this question right away: “”It doesn’t matter. Effort driven … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged | 4 Comments

How to calculate work, and then fix it in IN MS PROJECT 2016

Hi, friend of mine has a Specific problem. He wants MS PROJECT. I will show you this problem with MS PROJECT 2016! Project has one Task: Resources are: As you can see there are Workers with 800% capacity, Laborers with … Continue reading

Posted in Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, PMI, PRoject Management | Tagged | Leave a comment