Category Archives: Microsoft Project 2013

How to Assign different Overtime Rate in MS PROJECT 2013

  Hi, in one of my Posts I have explained how to calculate and work with Overtime hours in MS Project 2013, so I am not going to do it again. This time I will explain how to apply different … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , | Leave a comment

How to replace Generic resources with those with specific skills in MS PROJECT 2013

Hi, again my Blog Reade has a Problem. Here it is: “I have a challenging task to transition unorganized planning in my company to using ms project professional 2010 with share point site. We have generic resources like developers, testers … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft SharePoint, PMI, PRoject Management | Tagged , , , | Leave a comment

Work without Resources in MS PROJECT 2013! Is it possible?

Hi, again I have a question from my Blog Reader: “Can you advise me how to handle a closed task that has a resource assigned, but the resource will eventually spend 0 hours. So it is in fact a 100 … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , | Leave a comment

How to manage Projects with SharePoint 2013 and MS PROJECT Professional 2013 – Part 2

Hi! Here is Scenario! I want to Manage my Project in MS PROJECT PRO 2013! I want to upload an mpp file in SharePoint 2013, and there I want to have all my Project Documents, and I want to track … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft SharePoint, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | Leave a comment

How to manage Projects with SharePoint 2013 and MS PROJECT Professional 2013 – Part 1

Hi, when you will read this post I’ll be at Adriatic coast, enjoying my holidays. In this post I’ will explain how to manage Projects thru SharePoint 2013, and how to connect them with MS PROJECT 2013! Be aware of … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 1 Comment

How to compare Projects in MS PROJECT 2013

Hi, in may cases you will have more than one Microsoft Project file for the same Project. Usually this is called versioning! And, after some time you will want to know where are the differences between two versions of your … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 4 Comments

Resource pool and subprojects in MS PROJECT 2013!

Hi, again one of my Blog readers has a problem: “I followed your instructions but I am running into a small issue. While my master project shows all the sub-projects and the attached resource pool in the resources sheet, when … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 12 Comments

Fixed Duration and effort driven Task in MS PROJECT 2013

  Hi, My Blog Reader has a problem: “Just a question. When I assigned a task to Fixed Duration, WITH EFFORT DRIVEN I see that Project has calculated some of the resources to work 50% or 33%. How does that … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , | 14 Comments

Resource vs. Task Calendar in MS PROJECT 2013 – PART 2

Hi, If you red my previous Post, you learned how to create Task Calendar, and force Resource to work on it on weekend. Is there another way? Yes it is! Credits to my Blog Reader for this post. Let’s say … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PRoject Management | Tagged , , , | 3 Comments

Resource vs. Task Calendar in MS PROJECT 2013

Hi, another question from my Blog reader: “How do you determine whether to create a task calendar or a resource calendar?For example I start off with setting up the project calendar as standard, and then I decide that a particular … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 7 Comments