Inactive Tasks and Actuals in MS PROJECT 2016
Hi, I saw very interesting discussion in LinkedIn, about making Task Inactive if it has actuals. First let me show the “issue”. I will create brand new Project in MS PROJECT 2016: and I will create John as Resource with … Continue reading
Day rates per resources in Microsoft Project 2016
Hi, I have the question from my Blog reader: “After trying for weeks, I’m trawling the net for Microsoft Project, to find out how to add day rates per resource to the schedule. I can do this in SAP, but … Continue reading
Actual duration for manually entered actual work in MS PROJECT 2016
Hi, I have a question from my Blog reader, and I’m going to explain the problem step by step. Of course I will use MS PROJECT 2016! My blog reader’s problem is written with Italic. 1. Let’s create a 5 … Continue reading
Effort without specific Tasks in Projects using Microsoft Project 2016!
Hi, often I have a question like this: “How to assign Work to someone when that work is not to be linked with any specific Task?”. I will show you how with MS PROJECT 2016! But first I have to … Continue reading
Over allocation not shown in MS PROJECT 2016 with Windows 10–Bug or not?
Hi, My blog reader has a problem. He explained it step by step, and I will answer at it in the same way. Project in certain instances doesn’t flag over allocated resources.For example, I created a resource John and assigned … Continue reading
Multiple relationships between Tasks – using dummy Task in MS PROJECT 2016
Hi, my last post Multiple relationships between Tasks–is this possible?, caused a lot of reactions. all of them are about using dummy Task. Here is one of them: “Insert a dummy milestone to carry part of the logic between the … Continue reading
Multiple relationships between Tasks–is this possible?
Hi, I have a great question form one of my Blog readers: “Hi Nenad, thanks for your time and experience. I have a question:I have to tasks 1 and 2.Task 2 starts with 1 day of delay of the start … Continue reading
How to show different Baseline in Gantt Chart–MS PROJECT 2016
Hi, I’ve got a question about MS PROJECT 2016: “Dear Nenad,How we can have a new baseline (adding task or resource and delete task or resource) and how viewing that new baseline on the Gantt Chart.” I will show you … Continue reading
Task Calendar and Resources – how they fit together in MS PRIJECT 2016?
Hi, I had a lot of question about the Topic I will write about today. Basically it is about relations between Resource (with no Calendar, or, to be more precise, which has Standard Calendar assigned), and specific Task with Specific … Continue reading
Scheduled Start and Scheduled Finish fields in MS PROJECT 2016
Hi, today I will explain two fields, not so often used in MS PROJECT 2016: Scheduled Start and Scheduled Finish. First I will create one simple Project with three Tasks, connected like this: As you can see Scheduled Start is … Continue reading