Actual start and finish date with material Resources in MS PROJECT 2013! When it does make a sense, and when it does not!

Hi,

in this Blog Post I will show you how to use Actual Start and Finish date with Material Resources in a proper way. Of course, using MS PROJECT 2013!

First I’m going to create brand new Project:

image

As you can see I will make a Backup, and a Cake in the same project Smile

Now I’m going to create some resources:

image

Now I’m going to assign Resources to Tasks:

image

and then for a Cake:

image

as you can see I need Mary, and 10 eggs for the cake!

Now I’m going to switch to Task Usage View:

image

As you can see, for the Cake Mary will use 5 eggs first day, and 5 eggs second day! Does it make a sense. NO! So I will change that, so Mary will use all eggs in day no. 1:

image

and:

image

and you will get:

image

Now I will “schedule” eggs in Wednesday 10.06.2015:

image

and I will get:

image

Now it make a sense, doesn’t it?

Let’s say that our Backup was started and finished at Thursday, 11.6.2015:

image

and I will get:

image

Everything is just perfect. Now, let’s say that Mary started with making a cake at Wednesday, 10.06, and finished at Thursday, 11.06:

image

and I’ll get:

image

So far, so good! BUT! Le’s say that I spent those famous eggs at Friday, 12.06:

image

and I will get:

image

WOW! Wonderful! Mary made a cake without eggs, at Wednesday and Thursday, and Eggs were jumped in the cake from the blue at Friday! Magic eggs!! Smile I’m kidding, of course. You can see that this Scenario doesn’t make a sense at all.

You should be very careful when you put Actual Start and Finish dates for Material Resources, according to work (People) Resources.  That is my point!

Best wishes!

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | Leave a comment

Actuals on Summary Tasks in MS PROJECT 2013

Hi,

today I will answer on may questions I’ve got from my Blog Readers, regarding to entering  % Complete, and Actual work in Summary Task, instead in Sub Tasks. I will do it in MS PROJECT 2013!

As always, I’m going to create simple Project:

image 

few Resources:

image

and I will assign Resources to Sub Tasks:

image

As you can see I added % Complete, Work, and Actual work in Gant Chart View.

Now suppose that I finished all Tasks below Summary Task 50%, on time. I will put 50% in % Complete, and I will get:

image

WOW! Did you expect something else? I bet you did! I will explain the results:

  • Total work is 88 hours
  • I have two “branches”: Task1 – Task 3 (Branch 1), and Task 4 (Branch 2)
  • 50% Complete means I have 44 hours completed.
  • Since I have two branches, 44 / 2 = 22, e.g. 22 hours was spent on Branch1, and 22 hours on Branch 2
  • Task 1 has 8 work hours, so it is 100% completed. Task 2 has 16 work hours, and I have 14 hours remaining (22 – 8 spent on Task 1 = 14). So % complete is 14/16 = 0,87 (87%). There is no remaining available hours for Task 3 so it remains at 0%
  • Task 4 (from Branch 2) has Actual work 22 hours (as explained above), and it has 40 hours Work so it is 22/40= 55% completed.

Let me give you another example. I will create New Schedule like this:

image

  • I have 3 Branches (Branch 1: Task 1 – Task 2, Branch 2: Task 3 – Task 4, and Branch 3: Task 5)
  • Forget about over allocation, it is not important for our case.
  • Total hours (work) is 216 hours: Branch1: 40 hours, Branch 2: 80 hours, and Branch 3: 96 hours).
  • Now I will make Summary Task 50% Completed:

image

  • 50% complete from total Work is 216 / 2 = 108 hours
  • Since I have 3 Branches those hours will be distributed among those branches with 108 / 3 = 36 hours per Branch
  • Task 1 in Branch 1 has 16 hours work, so it is 100% completed. Remaining hours for distribution in this branch is 36-16=20 hours
  • Task 2 in Branch 1 has 24 hours work, actual work is 20 hours, so it is 20/24=83% completed. Remaining hours for distribution in 0 hours
  • Task 3 in Branch 2 has 40 hours work, actual work is 36 hours, so it is 36/40=90% completed. Remaining hours for distribution in 0 hours
  • Task 5 in Branch 3 has 96 hours work, actual work is 36 hours, so it is 36/96=38% completed. Remaining hours for distribution in 0 hours

But what if I did not put anything in %Complete field, but I put 108 hours in Actual work field in Summary Task? What would happen? Same as I put 50% in %Complete in Summary Task field!

You do not believe me? Try it!

Regards!

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010 | Tagged , , , | Leave a comment

When and why assign Resources to Summary Tasks and Milestones in MS PROJECT 2013!

Hi,

I got a question from one of my Blog Readers: “Hi, would you be so kind and explain when to assign Resource to Summary Task or Milestone!”

I will explain how to do it (which is very easy), and when and why (which is my point of view). Of course, I will  use MS PROJECT PRO 2013!

First I am going to create brand new PROJECT:

image

and one Resource:

image

Now suppose that John is Project Manager, and by default, he is responsible for whole Project. What will you get if you assign him to Summary Task, like that?:image

Notice, that I added Cost and Work columns in Gantt Chart View. First of all you might think (wrong), that since John is assigned to the Summary Task, his work (in hours) will be spread among all Subtasks. No! MS PROJECT will calculate all work from subtasks, and it will assign those hours to the Summary Task, without assigning hours to the Subtasks. Now I will add one new Task but I will not put any Predecessor to it:

image

Notice that nothing changed, since New Task is shorter in Duration than whole Summary Task Duration. But now I’m going to put 10 days in New Task Duration, and I will get:

image

You can see that Total Cost for Summary Task is $12.000 (10 days * 8 hours per day * $ 150 per hours), and total Work is 80 hours (10 days * 8 hours). TIP TIME! Do not assign any Resource to Summary Task! If you want to get real work in hours and real Cost, assign john to all Tasks, instead of Summary Task like that:

image

Here you can see “real” work, “real” costs, and – John is overallocated! HURAAAA!

If John is responsible person for Summary Task, but he will not spend any time during execution, you can assign him to the Milestone:

image

With that you do not have any Costs or work Hours, but you can still filter all Milestones and John as Resources and see when something should be finished, and for which milestones is he responsible!

Regards!

Posted in Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , | 2 Comments

Manually Scheduled Summary Tasks, and Subtasks in MS PROJECT 2013

Hi,

Today I will explain how to use Manually Scheduled Summary Tasks and its Subtasks in MS PROJECT 2013

First I will create new Project, and then I will create one Manually Scheduled Summary Task, like in picture below:

image

Now I will create three Subtasks, and I will link them:

image

Finally I will make those Tasks as Subtasks:

image

and I will get:

image

Notice that there is a difference between Summary Tasks, and Subtasks, because Summary Task is supposed to have 5 days duration (manually entered), but auto schedule (Subtasks), are supposed to have 7 days duration. Finish date has red underline, and on the left side of the Screen there is a red bar, which warn me that something is wrong:

If I hoover mouse under Finish date field I will get:

image

So I will Right-click at the Finish date field, and I will get:

image

I will choose: Fix in Task Inspector, and I will get:

image

As you can see I have two options:

  1. Move Finish date: It will move finish date to 19.05.2015, which is proper date, according to Schedule, but it will keep Summary Task in Manually Scheduled mode
  2. Auto Schedule: It will switch Task from Manually to Auto Scheduled mode, and move the date to the 19.05.2015, as well

The real question is: Why should anyone has Summary Task in Manually scheduled mode? The answer is very Simple: In planning phase you can have top-down approach, so you will first plan your Summary Tasks, and then you will see the “real” situation, when you will now much more about tasks which should be done to accomplish Summary Tasks. After you see a difference, you should decide what are you going to do. Are you cut the Scope, or maybe crash or fast track your tasks, or you will extend the whole duration. Whatever you do remember this advice: When you are finished with planning phase, and before you save your plan as a Baseline, turn all Summary Task  to Auto Mode. It is best approach!

Regards Smile

 

1.

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2010, PMI | Tagged , , , | 1 Comment

Maximal Units and Default Values in MS PROJECT 2013

Hi,

my Blog Reader is in trouble. He wrote:
”Hi Nenad,

I am in need of a favor from you. I am currently working with the MS project to accomplish the team utilization and also to forecast the team’s availability. I am trying to assign a Generic team (3 developers) . In the resource sheet have set the max % to 300%. But when I assign this resource to a task and set the works hours , it calculates the duration based on 100% units only. Do I need to go and change the units in the resource tab for each task to 300%. When the percentage is below 100% , it does calculate automatically from the resource sheet mentioned.”

First of all, what is Max Units in Resource Sheet? It is Maximal capacity that Resource can work per day on one or multiple tasks without over allocation. For example, if working hours in Calendar are from 0800 to 12:00, and from 13:00 to 17:00, with 8 hours working day, and it’s Capacity is 100% he or she can work 8 hours per day without over allocation. If it’s Maximal capacity is 50% he or she can work only 4 hours per day without over allocation, and if it’s capacity is 300% he or she can work 24 hours per day.

Now let me show this in MS PROJECT 2013! First, I will create one Task:

image

I will create two Resources: John with 50% Max Units, and Team A with 300% Max Units:

image

Now I will assign both Resources to the Task via Gantt Chart:

image

and I will get:

image

As you can see John will work only 50% (his Max units), but Team A will work not 300% but 100% instead.

Let’s take a look at the Task Usage View:

image

As you can see, John will work 4 hours per day (50%), and Team A 8 hours per day (100%).

If I want to assign Team A with 300% (it’s May units) I must put that amount manually:

image

Finally, I will get (in Task Usage View):

image

As you can see, now Team A will work 24 hours per Day!

To conclude, if You assign Resource to the Task, it’s maximal Capacity to this Task is:

  • If Max Units in Resource Sheet is 100% = 100% for Task
  • If Max Units in Resource Sheet is less than 100% = Max Units from Resource sheet for Task
  • If Max Units in Resource Sheet is greater than 100% = 100% for Task

And, Max Units that is greater than 100% in Resource Sheet tells you how much Capacity that Resource has per Day, not how much will it work on single Task, unless you tell MS Project that you want that Resource to work more than 100% for that Task!

 

Regards!

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 7 Comments

Multiple Critical Paths in MS PROJECT 2013

Hi,

today I will show you how to use Option: Calculate multiple critical paths in MS PROJECT 2013!

What is Critical Path indeed?  This is the longest path which show you how long will a Project Duration be. It is also a path in which if any task is late, the whole Project will be late. So, it has no Slack!

OK! Let me create brand new Project:

image

or, graphical View:

image

Now I’ll switch to Detail Gantt View:

image

As you can see Critical path is on upper branch of Tasks. Task 4, and Task 5 have Slack = 9 days. It means that they can slip for 9 days without affecting Project end date.

Because Task 4, and Task 5 are in independent branch you can consider this branch Critical as well. So, if you want to see those Tasks as critical you should follow this steps:

image 

then:

image

and then:

image

and you will get:

image

Now you see both branches (independent) as Critical.

Let me give you an advice. It doesn’t make a sense to have multiple independent branches in a Project. You should always have one common Task at the end of the Project, or at least, one milestone. I always have a milestone at the end of the Project.

I will create one and I will put Task 3, and Task 6 as Predecessors to that milestone:

image  

Let’s look at Detail Gantt again:

image

Now, I have only one Critical Path, and Option: Calculate multiple critical paths is still on.

And this is best practice how to make right Schedule for your Project. To conclude, avoid independent branches in you Project!

 

Regards!

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , | Leave a comment

Status Date line in MS Project 2013!

Hi,

I’ve got a simple question from one of my Blog readers: “Hi, in your examples I can see Status Date in a Gantt Chart View. But I can not see it in my Projects. How to get this?”

The answer is very simple, and I will show you how to get it with MS PROJECT 2013!

First I’m going to create new Project like this:

image

You can see a thin green line which show the Current Date. Now I’m going to set the Status Date for My Project:

image 

and I’ll get:

image

As you can see It is not visible at the Gantt Chart. Now, follow next steps:

image

and then:

image

and you will get:

image

IT is easy, isn’t it?

Regards!

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 2 Comments

Split in progress Task option in MS PROJECT 2013!

Hi,

My very good friend Ben Howard, find a problem, and a solution. I will share it with you. But before you continue to read this Post please taka a look on his great site: www.applepark.co.uk. Do I have to mention that he is MVP? No, I do not!

I will first create a brand new Project in MS PROJECT 2013:

image

I have two Tasks, both with 5 days Duration, and Task 2 is successor of Task 1. I want that Task 1, start exactly at 31.3.2015, and I will make a Hard “Must Start On” constraint on it:

image

and I will get:

image

Now suppose that I’m 80% done with Task 1:

image

and then:

image

and I will get:

image

Now I will set Status date to Friday, April the 3th:

image

and I will move uncompleted work after the Status Date:

image

and I will get:

image

As you can see, nothing happened, as expected. Suppose now that I started with work on Task 2, at April the 1st:

image

and then:

image

I will get:

image

 

Is it a Bug? No it is not. Even if I said that I was started with Task at April the 1st, Status date is April the 3th so it can not be actually started before Status date.

But if I want to do it anyway I can first uncheck this option:

image

and then:

image

and then:

image

Now if I move Project to status date, and enter Actual Start to April the 1st (I will not repeat Pictures which you can see above), I will get:

image

So I got, what I want.

Remember, with Split in-progress tasks, you can report Task progress ahead of the Schedule once you Reschedule Project after the Status Date!

 

Thanks Ben 🙂

Regards!

Posted in Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | Leave a comment

Duration with different Resources working time in MS PROJECT 2013!

Hi,

with permission of my MVP friend Gérard Ducouret I will explain how different Resources working time affect Task duration in MS Project 2013!

I will show you on the example. First, I will create (as I always do), the brand new Project:

image

I will create two Resources, one will work 8 hours per day, and the other 7 hours per day:

 image

I will now change Standard Calendar for Resource – 7 hours:

image

and then:

image

As you can see, this Resource will work only 7 hours per day.

No I will assign Those Resources to Tasks:

image

Both, Task 1, and Task 2 has 10 days Duration, but the whole Project has 11,38 days of Duration. Why? Let’s look at the Task Usage View (I will make two Pictures):

image

As you can see Task 1 will be finished at Tuesday 31.3.2015 (two day later than Task 1).

Here is the second part of Task Usage View:

image

Both Task need 40 hours of work to be done! Why? Hit File Tab, then Options, and then:

image

So to finish each Task with 10 day Duration it will be needed for 80 hours (10 days * 8 hours per day)

Task 2 will be done with Resource who will work 8 hours per day, so it will start at Monday, and it will be Finished next Friday, because 80 hours = 80 / 8 hours per day = 10 days,

Task 1 will be done with Resource who will work 7 hours per day, so it will start at Monday, and it will be Finished at Tuesday after two weeks. Where the 11,38 days is coming from? If you look at the second picture form the Task Usage View, you will see that Resource – 7 hours per day will work 11 full days (7 hours per day), and at last day it will work only 3 hours, eg 3/8 = 0,38 days. So 11+0,38 = 11,38 days.

I know what you do not understand! Why is duration for Task 1 = 10 days! Frankly, I do not know. From my point of view  it should be 11,38

Now let’s look at the Detail View:

image

This is Fixed Units Task type.

But what if you want that both Task have 10 days duration, no matter who will work on them, and how many hours will someone work on them?

I will now change this to Task to Fixed Duration type:

image

Now Task has “right” Duration, but that is not what I want! I will change Duration to 10 days:

image

and I will get:

image

or / and (Second Picture):

image

It’s tricky, isn’t it?

Regards!

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , | Leave a comment

Updating Project to status date versus Leveling in MS PROJECT 2013

Hi,

yesterday I was teaching one of my Blog Readers about Leveling and Updating Projects in MS PROJECT 2013. The main problem was that after updating Project over allocated resources are still over allocated. I will explain the difference between those two things. I will not going to deep in Leveling in this Post.

Let me create The brand new Project:

image

and I will create one Resource:

image

Finally I am going to assign John to all Tasks:

image

Obviously, John is very, very over allocated.

Let say that John has Finished Task 1, and Task 4, and 50% of Task 2, and then he got Sick:

image

Now suppose that today is Friday, 13.03.2015, and we are going to update our Project to get Real Situation before we go home and spend wonderful weekend:

image

I will now update this Project:

image

and I will get:

image

as you can see, John is still over allocated. Why? Because I rescheduled Project after status date and get real situation. With this option you will never resolve Over Allocation. This is not a bug, OK, now suppose that I talked to John and I asked him why he got sick? The answer can be: “Because I am working far to much per day!” So I want to be sure that John is not Over allocated any more. Firs I will look at the Resource Usage View:

image

Now I know that John has to work 16 hours per day at Monday, Tuesday , and Wednesday. Now I will Level him:

image

and I will get:

image

As you can see John will work on Task 5, after Task 3, from Friday to Tuesday, and he is not over allocated any more. So there is a huge difference between Updating Project to status date versus Leveling Resources, and you should be aware of it.

Regards!

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , | 1 Comment