Microsoft Project 2016 and Kanban!
Hi, in my previous post I wrote about Microsoft Project 2016 and Scrum. Now, I will show you some other things, based on Kanban Agile methodology. This post will be much shorter than previous one, because you can use everything … Continue reading
Microsoft Project 2016 and SCRUM
Hi, as I promised, today I will cover Scrum with MS PROJECT 2016! But, first of all what do we need form Scrum (I will talk what we need – by the book)? We need: Product Backlog and Sprint Backlog. … Continue reading
Microsoft Project 2016 goes Agile! YEAH!
Ladies and Gentleman, all Project users, as you know Microsoft Project was intended for all kind of Projects, but let’s be honest, it wad made only for Waterfall Projects. From now on, that is history. Microsoft Project goes Agile – … Continue reading
Additional Resources assigning to the Task which have work in progress in MS PROJECT 2016
Hi, Today I’m going to explain what happens if I assign additional resource in Task which has a progress with MS PROJECT 2016. First, I’m going to create brand new Project: I have two resources available: I will assign John … Continue reading
Overtime Work and Fixed Duration in MS PROJECT 2016!
Hi, today I’m going to show relation between Fixed Duration Task Type, and Overtime Work in MS PROJECT 2016. First I’m going to create a simple Project with one Task – Fixed Duration: As you can see In the Gant … Continue reading
Overtime work at specific day–is it possible in MS PROJECT 2016?
Hi, In this post, I will show you answer to one of my blog readers. He asked me is it possible to put Overtime Work at specific day in MS PROJECT 2016? Let’ say that we have a simple Project, … Continue reading
Inactive Tasks and Actuals in MS PROJECT 2016
Hi, I saw very interesting discussion in LinkedIn, about making Task Inactive if it has actuals. First let me show the “issue”. I will create brand new Project in MS PROJECT 2016: and I will create John as Resource with … Continue reading
Day rates per resources in Microsoft Project 2016
Hi, I have the question from my Blog reader: “After trying for weeks, I’m trawling the net for Microsoft Project, to find out how to add day rates per resource to the schedule. I can do this in SAP, but … Continue reading
Actual duration for manually entered actual work in MS PROJECT 2016
Hi, I have a question from my Blog reader, and I’m going to explain the problem step by step. Of course I will use MS PROJECT 2016! My blog reader’s problem is written with Italic. 1. Let’s create a 5 … Continue reading
Effort without specific Tasks in Projects using Microsoft Project 2016!
Hi, often I have a question like this: “How to assign Work to someone when that work is not to be linked with any specific Task?”. I will show you how with MS PROJECT 2016! But first I have to … Continue reading