Working with Graphical Indicators in MS PROJECT 2010

  Hi, in this Post I’ll show you how to use graphical Indicators in MS PROJECT 2010. Here is The Scenario: I have may Project Baseline (and this is my Project Plan) I am tracking the Project Progress If my … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, MS PROJECT 20101, PMI, PRoject Management | Tagged , , , , | 2 Comments

How to work with Outline Codes in MS Project 2010?

  Hi, in my last Post I have explained how to use custom fields in MS PROJECT 2010. One of custom field type is Outline Code. Suppose that you have resources group by skills like this: Developers  (101 – C# … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 7 Comments

Customizing fields and specifying Lookup Values for a Custom Fields

  Hi, in this Post I will explain how to use custom fields in MS PROJECT 2010. There are nine types of Custom Fields in MS PROJECT 2010: Cost. Use this type when you need a field in which you … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 9 Comments

Customizing Views in MS PROJECT 2010 – Part 2.

  Hi, in my previous Post I have explained how to copy one View to another, and make a customization. Notice that are two different types of View in MS PROJECT 2010: Single View, and Combination View. Example of Single … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 3 Comments

Customizing Views in MS PROJECT 2010 – Part 1.

  Hi, I will explain Views in MS PROJECT 2010 PROFESSIONAL! First I will create an example. I have a Project with four Tasks: and four Resources: and those Resources are assigned to Tasks: OK! This is Gantt Chart. In … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | Leave a comment

How to apply Overtime, and Double time rates in MS PROJECT 2010

  Hi, one of my Blog reader has a Problem. She has Project and she must apply three different Pay rates for Resource on the Task in MS PROJECT 2010.  Here is an example: John is working on task, and … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, MS PROJECT 20101, PMI, PRoject Management | Tagged , , , | 32 Comments

How to Collaborate between MS PROJECT 2010 Professional and MS SharePoint – Part 2

  Hi, I will show you how to synchronize Tasks between MS PROJECT 2010, and SharePoint. Here are the Tasks in MS PROJECT 2010: and in SharePoint: Notice that they are same! No I will change some fields in MS … Continue reading →

Posted in MICROSOFT PROJECT, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 4 Comments

Managing Multiple Projects with MS PROJECT 2010 – Part 2

  Hi, In my previous post I have described how to put subprojects in a Project, and how to make “Master-Slave” Relationship in MS PROJECT 2010. It looks like this: I want to see Critical Path: and I will get: … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 15 Comments

Managing Multiple Projects with MS PROJECT 2010 – Part 1

Hi, I will explain how to Manage Multiple Projects with MS PROJECT 2010. Before I start, I have to tell you something very important. If you are going to manage multiple Projects as a Program, or Portfolio, or both, and … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 26 Comments

Sharing Resources among Projects with MS Project 2010 – Part 2

  Hi, in my previous post I have explained hot to create and use the Resource pool.  Suppose that you want to open your project file which uses a Resource pool in MS PROJECT 2010. You will get: My strong … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 5 Comments