Author Archives: Nenad Trajkovski
Day rates per resources in Microsoft Project 2016
Hi, I have the question from my Blog reader: “After trying for weeks, I’m trawling the net for Microsoft Project, to find out how to add day rates per resource to the schedule. I can do this in SAP, but … Continue reading
Actual duration for manually entered actual work in MS PROJECT 2016
Hi, I have a question from my Blog reader, and I’m going to explain the problem step by step. Of course I will use MS PROJECT 2016! My blog reader’s problem is written with Italic. 1. Let’s create a 5 … Continue reading
Effort without specific Tasks in Projects using Microsoft Project 2016!
Hi, often I have a question like this: “How to assign Work to someone when that work is not to be linked with any specific Task?”. I will show you how with MS PROJECT 2016! But first I have to … Continue reading
Over allocation not shown in MS PROJECT 2016 with Windows 10–Bug or not?
Hi, My blog reader has a problem. He explained it step by step, and I will answer at it in the same way. Project in certain instances doesn’t flag over allocated resources.For example, I created a resource John and assigned … Continue reading
Multiple relationships between Tasks – using dummy Task in MS PROJECT 2016
Hi, my last post Multiple relationships between Tasks–is this possible?, caused a lot of reactions. all of them are about using dummy Task. Here is one of them: “Insert a dummy milestone to carry part of the logic between the … Continue reading
Multiple relationships between Tasks–is this possible?
Hi, I have a great question form one of my Blog readers: “Hi Nenad, thanks for your time and experience. I have a question:I have to tasks 1 and 2.Task 2 starts with 1 day of delay of the start … Continue reading
How to show different Baseline in Gantt Chart–MS PROJECT 2016
Hi, I’ve got a question about MS PROJECT 2016: “Dear Nenad,How we can have a new baseline (adding task or resource and delete task or resource) and how viewing that new baseline on the Gantt Chart.” I will show you … Continue reading
Task Calendar and Resources – how they fit together in MS PRIJECT 2016?
Hi, I had a lot of question about the Topic I will write about today. Basically it is about relations between Resource (with no Calendar, or, to be more precise, which has Standard Calendar assigned), and specific Task with Specific … Continue reading
Scheduled Start and Scheduled Finish fields in MS PROJECT 2016
Hi, today I will explain two fields, not so often used in MS PROJECT 2016: Scheduled Start and Scheduled Finish. First I will create one simple Project with three Tasks, connected like this: As you can see Scheduled Start is … Continue reading
How to show duration in different units for the same Task in MS PROJECT 2016
Hi, today I’m going to show you ProjDurConv function which is very useful in MS PROJECT 2016. Here is the Scenario. Suppose that I have a simple Project with one Task, and it’s Duration is 5 days: I want to … Continue reading