Multiple Costs types for Resource in a same Task
Hi, I have very interesting question from on of my Blog readers: “I have a problem with MS Project: I don’t know how to manage 2 type of cost for 1 person, I mean, I have 1 employee with 100USD … Continue reading
New way of choosing Predecessors and Successors in MS PROJECT 2016
Hi, If you work with the latest version of MS PROJECT 2016, and you have update it regular you will notice one great improvement in Predecessor field. Let me show you that. First I will create brand new Project with … Continue reading
Multiple assignments on the same Task in MS PROJECT 2016
Hi, my Blog Reader has a very interesting question: “Hi Nenad I have a problem, and I hope you can help me, I’m a follower of your blog. I have some task on project and resources, but I want … Continue reading
Resource with assignment 0%–what is it?
Hi, You can find a lot of examples when you can see that it is possible to assign Resource to Tasks with 0% Units. In this post I will show you how can you do it, and what would happen … Continue reading
How to automatically change Material relative to Scope change in MS PROJECT 2016
Hi, I’ve got very good question from one of my Blog readers: “Hi,I am a novice. Tried to find some solution to a certain scenario in your blogs but browsing through some dozen articles, I thought it better to ask … Continue reading
Task Summary Name–new field in MS PROJECT 2016
Hi, There is one new Task related field in MS PROJECT 2016: Task Summary Name. It is very useful. Usually Summary Tasks have a lot of subtasks, and when you group them, filter them or just look at them, you … Continue reading
Baseline in Master and Sub-Projects with MS PROJECT 2016
Hi, we all know what the Baseline is. But where is the right place to make it, if we have a Project which is Subproject of Master Project. I will show you where with MS PROJECT 2016. First of all … Continue reading
Subproject File field in MS PROJECT 2016
Hi, today I will show you one interesting field in MS PROJECT 2016, called Subproject File. Let me first create three simple Projects: and: and finally: Those Project are saved locally. Now I will create Master Project and I will … Continue reading
Posted in Uncategorized
1 Comment
Assignment Delay field in MS PROJECT 2016
Hi, in Microsoft Project 2016 there is one very useful field called: Assignment Delay. Let me show you how useful is it, and how can you use it. First, as I always do, I will create simple Project: I will … Continue reading
Project Summary Task and Calendars in Microsoft Project 2016
Hi, I have interesting question from my Blog reader: “How does one change the calendar for the Project Summary Task? The schedule is developed and has a calendar, other than the standard calendar, associated with all the tasks, but … Continue reading