Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!

Baseline for Subprojects in MS PROJECT 2013

Hi, Today I’m going to explain how to set and see Baseline for Subprojects in MS PROJECT 2013, and how to see those Baselines in Master Project! First I’m going to create two Brand new Projects with one Task: and … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , , | 3 Comments

How to Assign different Overtime Rate in MS PROJECT 2013

  Hi, in one of my Posts I have explained how to calculate and work with Overtime hours in MS Project 2013, so I am not going to do it again. This time I will explain how to apply different … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , | Leave a comment

How to replace Generic resources with those with specific skills in MS PROJECT 2013

Hi, again my Blog Reade has a Problem. Here it is: “I have a challenging task to transition unorganized planning in my company to using ms project professional 2010 with share point site. We have generic resources like developers, testers … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft SharePoint, PMI, PRoject Management | Tagged , , , | Leave a comment

Work without Resources in MS PROJECT 2013! Is it possible?

Hi, again I have a question from my Blog Reader: “Can you advise me how to handle a closed task that has a resource assigned, but the resource will eventually spend 0 hours. So it is in fact a 100 … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , | Leave a comment

The answer my friend is blowing in the wind!!!

Dear Blog Readers, I have lot of questions, but I am on my Vacation with very restricted mail access! So,  I’ll will start answering next week! Love you!

Posted in Uncategorized | Leave a comment

How to manage Projects with SharePoint 2013 and MS PROJECT Professional 2013 – Part 2

Hi! Here is Scenario! I want to Manage my Project in MS PROJECT PRO 2013! I want to upload an mpp file in SharePoint 2013, and there I want to have all my Project Documents, and I want to track … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft SharePoint, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | Leave a comment

How to manage Projects with SharePoint 2013 and MS PROJECT Professional 2013 – Part 1

Hi, when you will read this post I’ll be at Adriatic coast, enjoying my holidays. In this post I’ will explain how to manage Projects thru SharePoint 2013, and how to connect them with MS PROJECT 2013! Be aware of … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 1 Comment

How to compare Projects in MS PROJECT 2013

Hi, in may cases you will have more than one Microsoft Project file for the same Project. Usually this is called versioning! And, after some time you will want to know where are the differences between two versions of your … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 4 Comments

Resource pool and subprojects in MS PROJECT 2013!

Hi, again one of my Blog readers has a problem: “I followed your instructions but I am running into a small issue. While my master project shows all the sub-projects and the attached resource pool in the resources sheet, when … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 12 Comments

Fixed Duration and effort driven Task in MS PROJECT 2013

  Hi, My Blog Reader has a problem: “Just a question. When I assigned a task to Fixed Duration, WITH EFFORT DRIVEN I see that Project has calculated some of the resources to work 50% or 33%. How does that … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , | 14 Comments