Category Archives: MICROSOFT PROJECT

Importing Resources from Excel into MS PROJECT 2013 and PROJECT 2016–VIDEO IS HERE!

I’m proudly announce that Webucator (www.webucator.com) recorder the Video https://www.youtube.com/watch?v=mniDdkKxgpM&feature=youtu.be of my Blog Post which you  can Find here: https://ntrajkovski.com/2015/02/27/importing-resources-from-excel-into-ms-project-2013/. If you want learn a lot about MS PROJECT, I strongly recommend that you visit their site https://www.webucator.com/microsoft-training/project.cfm, and you … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2016 | Tagged , | Leave a comment

Resource calendar vs. Task Calendar, and weekends in MDS PROJECT 2016

Hi, Again, I have a question from one of my Blog readers, which is related to my previous post: “Hi Nenad,¸ Thank you very mush. But can you please explain the following inconsistency in MSP behavior: If in the example … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , | 4 Comments

Resource Calendar and weekend!

  Hi, Again, I have a question from one of my Blog readers: “Nenad, I’m new to MS Project and really appreciate information on this site. I have a question regarding your post “Resource vs. Task Calendar in MS PROJECT … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , | 2 Comments

Task 0 in MS PROJECT 2016

  Hi, This post will be short, but very useful. I have a question from one of my Blog Readers: “Hi Nenad,I discovered hat my task number usually starts from 1 instead of 0.Kindly assist on this.” I will show … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged | 4 Comments

Task Duration and Resource additional day off in MS PROJECT 2016

Hi, today I will show you what happens if you assign resource to the Task, and afterwards put, for example, day off for that Resource in MS PROJECT 2016 First, I’m going to create simple Project: I will now create … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016 | Tagged | Leave a comment

How to change Task Finish date when Task has fixed amount of Actual work in MS PROJECT 2016

  Hi, friend of mine got a problem. He has Task in which he wants to put Actual work and Actual Finish date for the Task, but he got odd result. Let me show you a problem with MS PROJECT … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

How to delete all dependencies for one Task in MS PROJECT 2016

Hi, for the last post in this year I choose to show you a very simple Trick. What if you have one Task with multiple Tasks dependencies, and, for some reason you want to remove those dependencies in one step. … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Manually scheduled Tasks and Dependencies when changing Duration in MS PROJECT 2016!

Hi, today I’m going to show you what happens when you establish dependencies between manually scheduled Tasks in MS PROJECT 2016, and then change Duration. First I’m going create simple Project: Now I’m going to put Duration for each Task: … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged | Leave a comment

“Keep task on nearest working day when changing to automatically scheduled mode” option in MS PROJECT 2016

Hi, a lot of my Blog readers asked me about “keep task on nearest working day when changing to automatically scheduled mode” option in MS PROJECT! I will show you what is it, and how does it work in MS … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged | Leave a comment

Fixed duration Task and Resource Calendar

Hi, today I will explain how is Work field Calculated when you have Fixed Duration Task Type, and Resource Calendar. Of, course I will use MS PROJECT 2016! First, as I always do, I will create new Project with a … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2016 | Tagged | Leave a comment