-
Recent Posts
Archives
Categories
Category Archives: Micsrosoft Project 2016
How to Delay Project in MS PROJECT 2019
Hi all, I have a question from one of my Blog readers: “The project I am involve in is using only material resources and the unit rate for each resource did not change through time. Currently the project has more … Continue reading
Resource replacement whit already assigned resource on Task in Progress–MS PROJECT!
Hi, I’ve got a question from one of my blog readers: “Let’s suppose that I have a task “Task” with fixed work task type. Duration is 10 days. I assign 2 resource who work for 8hr per day. Total work … Continue reading
Customized resource calendar and its effect on task duration in MS PROJECT 2016!
Hi, my blog reader has a question and I’m going to repro his scenario step by step, and answer the question using MS PROJECT 2016. First I will create a 5 day Task: There are 2 resources assigned to the … Continue reading
Fixed Duration Tasks and Resource availability in MS PROJECT 2016
Hi, today I will show you what happens wen you have Fixed Duration Tasks with Resources assigned to them, and those resource are unavailable at the specific time. I will use MS PROJECT 2016 First I will create simple Project … Continue reading
Predecessors, Successors and Task form in MS PROJECT 2016
Hi, How often do you have a large Project with lot of Tasks? Hundreds of them. And your schedule is very complicated. And then, suddenly you have to change something. Maybe relations within Tasks, maybe your timeline is too long, … Continue reading
Delay on Task in progress with MS PROJECT 2016
Hi, today I’m going to show you where is the difference between Task in progress and delay, with MS PROJECT 2016. Let’s say that we have a simple Project with one single Task: and that we have John as Resource: … Continue reading
Assign Resources to different time on the same Task in MS PROJECT 2016
Hi, one of my Blog readers has a questions: “One activity has 3 days Duration, and we need to assign 2 resources. First resource will work all 3 days on it, but second is only needed for 2nd day. How … Continue reading
Recording task progress ahead of schedule in MS PROJECT 2016!
Hi, my Blog reader has a problem with scheduling Task ahead of planned time! I will reproduce his scenario in MS PROJECT 2016!. First I’m going to create simple Project with two Tasks: Now I’m going to create two Resources … Continue reading
Task Actual Start and Finish date when Resources are unavailable in MS PROJECT 2016
Hi, in this last post for year 2018. I will show you how Actual Start and Finish date are affected with Resource Calendar in MS PROJECT 2016. First I will crate Simple Project with one Task: I will create Two … Continue reading
How to change multiple Resources on Tasks in progress with MS PROJECT 2016?
Hi, today I will show you how to change multiple Resources when you have Tasks in progress with Microsoft Project 2016! Firs I’m going to create brand new Project with two simple Tasks: Now suppose that I have those Resources … Continue reading