Task Calendar in MS PROJECT 2013 – when to use it?

Hi, Again, I have a request (question) from one of my Blog readers: ! “Hello, Your tutorials are very helpful – thank you! I was wondering if it is possible to make a particular task not allowed on a particular … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | Leave a comment

Remove Resource Pool from MS PROJECT 2013

Hi, again, a question from one of my Blog readers: “Hello Nenad, How does one remove a resource pool from a master project completely from MS Project 2013. I can’t keep other sub projects that formerly were connected to the … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 7 Comments

Actual finish date in MS PROJECT 2013

  Hi, again, one of by Blog readers has a question: “How do you update actuals? Let’s say the task is supposed to have finished 21 Feb 2014 according to the original plan. However, this task can now be finished … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 4 Comments

Multiple Critical Paths in MS PROJECT 2013

Hi, we all know what Critical Path means. It is path in which, if any Activity is late, the whole Project is late. Let me show you Critical Path in MS PROJECT 2013. First I’ll create new Project with some … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 1 Comment

Some additional setup in MS PROJECT 2013

  Hi, first Blog Post in new 2014 year. I’ve been asked about some recommendations about additional setup in MS PROJECT 2013 There is a lot of setup which you can do in MS PROJECT 2013. You can set up … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI | Tagged , , , , | 9 Comments

Collapsing the Ribbon in MS PROJECT 2013

Hi, this will be an easy one, because tomorrow is a New Year (2014), so I’ll finish this year with an answer to my Blog Reader. The Problem is very Simple: “Dear Sir, I’m using the Ribbon all the time, … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 2 Comments

Work Package versus Activity in MS PROJECT 2013

  Hi, another question from one of my Blog Readers: “Hello; I have a question about “work package”. Is work package the same as “activity” or “activity” is more detailed than a work package? Thank you” Theory first. Suppose that … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 4 Comments

Generic Resources and different capacity in MS PROJECT 2013

Hi, again one interest question from my Blog reader: “Dear Nenad,Thank you VERY much for your very informative blog! I enjoy reading your posts and visit the site often. I would appreciate if you could answer my question regarding managing … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 4 Comments

Start and Finish Date with Auto Scheduled Task

Hi, first of all, apologies for delaying with my regular Post, but I was very busy with organizing SPCAdriatics (SharePoint and Project) conference last weeks (www.spcadriatics.com) Again, a question from one of my Blog readers: “Greetings Sir, Thanks kindly for … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 3 Comments

% Complete VS Physical % Complete in MS PROJECT 2013

Hi, I will explain hot to track Physical % Complete in MS PROJECT 2013. In MS PROJECT you can Track %Complete, % Work Complete, and Physical % Complete. Where are the differences? % Complete is about Duration % Work Complete … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 10 Comments