How to use Boards group by Progress in Project for Web
Hi, In my previous Posts I’ve created a simple Project for Web: This is View in Grid. Now let’s see Board Tab: All tasks are here! In the upper right corner I can choose between three type of Boards: So … Continue reading
Leveling Gantt view and Leveling Delay field in MS PROJECT 2019
Hi, today I will explain Leveling Gantt view and Leveling Delay field in MS PROJECT 2019, which are rarely used. I will crate a simple Project with two resources and they both are going to be overallocated: As you can … Continue reading
Resources with dynamic workload in MS PROJECT 2019
Hi, today I will show you how to deal with a problem which you will face, almost, in every Project. And that is: “Resources which are leaving Project, and coming back after some time to perform the same Task!”. Let’s … Continue reading
Traffic lights for work exceeded Baselined work in MS PROJECT 2019
Hi, Today I’m going to show you how to make a traffic light which will show you when your work has exceeded planed or Baselined work in MS PROJECT 2019! I’m going to create Simple Project with one Task: I’m … Continue reading
Posted in MS PROJECT 2019, PMI, PRoject Management
Tagged Micorosft Project 2019 - Work, MS PROJECT
Leave a comment
Changing Values in Project Summary Tasks in MS PROJECT
Hi, Today I am going to show you how to change Duration or Start/Finish date on Summary Task using MS PROJECT 2019. I am going to create simple Project with tow Tasks under one Summary Task, and I’m going to … Continue reading
How to reschedule Uncompleted Remaining Work for multiple Projects in MS PROJECT 2019
Hi, today I will show you how to reschedule uncompleted remining work for multiple Project in one step using MS PROJECT 2019 To do that, of course we should have those project in one Master project. First I am going … Continue reading
Posted in MS PROJECT 2019, PMI, PRoject Management
Tagged MS Project 2019 - Schedule
Leave a comment
Fixed work with Resources in shifts with MS PROJECT
Hi, last week I had great training with wonderful people in Oman, so this post is dedicated to all of them as a small THANK YOU. I will show a case in MS PROJECT 2019. Here is the Scenario. Factory … Continue reading
Posted in MS PROJECT 2019, PMI, PRoject Management
Tagged Micorosft Project 2019 - Shifts
Leave a comment
Resource replacement whit already assigned resource on Task in Progress–MS PROJECT!
Hi, I’ve got a question from one of my blog readers: “Let’s suppose that I have a task “Task” with fixed work task type. Duration is 10 days. I assign 2 resource who work for 8hr per day. Total work … Continue reading
Fixed cost for resource over the time period in MS PROJECT 2016
Hi, I’ve got a question from one of my Blog readers: “Mr. Nenad, I have a question please:Let’s suppose that I have a human work resource assigned to different tasks within the project. It receive each month a fixed salary … Continue reading
Resource detail form in MS PROJECT 2016
Hi, as I wrote many times there is a very useful Task form in MS PROJECT 2016! Here is one simple project: With the Task form we have full control over the Task, like this: In Task form we can … Continue reading