Tag Archives: Micorosft Project 2016
Fixed Duration Tasks and Resource availability in MS PROJECT 2016
Hi, today I will show you what happens wen you have Fixed Duration Tasks with Resources assigned to them, and those resource are unavailable at the specific time. I will use MS PROJECT 2016 First I will create simple Project … Continue reading
Predecessors, Successors and Task form in MS PROJECT 2016
Hi, How often do you have a large Project with lot of Tasks? Hundreds of them. And your schedule is very complicated. And then, suddenly you have to change something. Maybe relations within Tasks, maybe your timeline is too long, … Continue reading
“Real” daily work on Tasks in MS PROJECT 2016!
Hello, today I’m going to deal whit one significant question which basically has many answers, or none. How many hours to assign to Resource per day? Let me show you one very, very simple example. Let’s say that we have … Continue reading
Project management Task and Administrative work in MS PROJECT 2016
Hi, my blog reader has a question about Project management Task, and administrative work, and how to handle it in MS PROJECT 2016? Here is Scenario. This is Project Schedule: First of all, I will advice not to use Project … Continue reading
Fixed work Task Type with limited Resource availability in MS PROJECT 2016!
Hi, my Blog reader run into problem with limited Resource availability. I will show the scenario and explain it with MS PROJECT 2016. I will create simple Project with one Task, 4 day duration, and I will assign John to … Continue reading
How to “loan” Resources from non-critical to critical Tasks in MS PROJECT 2016
Hi, today I will explain one specific Case which one of my Blog users have. And I will do it by reproducing this Case step-by-step, using MS PROJECT 2016! There are three tasks with resources assigned to them: I will … Continue reading
Delay on Task in progress with MS PROJECT 2016
Hi, today I’m going to show you where is the difference between Task in progress and delay, with MS PROJECT 2016. Let’s say that we have a simple Project with one single Task: and that we have John as Resource: … Continue reading
Assign Resources to different time on the same Task in MS PROJECT 2016
Hi, one of my Blog readers has a questions: “One activity has 3 days Duration, and we need to assign 2 resources. First resource will work all 3 days on it, but second is only needed for 2nd day. How … Continue reading
Recording task progress ahead of schedule in MS PROJECT 2016!
Hi, my Blog reader has a problem with scheduling Task ahead of planned time! I will reproduce his scenario in MS PROJECT 2016!. First I’m going to create simple Project with two Tasks: Now I’m going to create two Resources … Continue reading
The Agile field in Microsoft Project online
Hi, In Microsoft Project Online, there is a new Field – Agile! I will show you what can you (or can’t) do with it! First I will create brand new Waterfall Project: and I will get: As you can see, … Continue reading