Category Archives: Microsoft PRoject 2010

My arm is broken! :-(

  Dear Blog Readers, Just an notice, that I broke my arm last Friday, so I will write my post a little bit “slower”! I hope that I will make a Post ‘till middle of the next week!   Regards!

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013 | Tagged , | 4 Comments

Resource Pool and Local Resources in MS PROJECT 2013

  Hi, I have a question from one of my Blog readers: “Hello, Nenad. First, I’d like to thank you by your posts. They are very helpful. Now, to my question. I have a central team coordinating and working in … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, PMI, PRoject Management | Tagged , , , , , | 2 Comments

How to apply different pay rates for Material Resources in MS PROJECT 2013?

  Hi, again, my Blog reader has a problem: “Hi dearfirst I would like to say thanks for your above post, after that I would like to share one question with you which I have in mind, it is also … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 4 Comments

Calendars and Moving Tasks to non working days in MS PROJECT 2013!

  Hi, again I have a question from my Blog Reader: “I liked your article and thought you may have an answer to a question I have.In Project 2010 with tasks set to Auto schedule if you schedule the start … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 11 Comments

How to assign 0$ costs for some Task with the same Resource in MS PROJECT 2013?

  Hi, one of my Blog readers has a problem: “Good morning, Sir. I have a slight problem with my project. For some tasks the cost of one resource for tasks is 0$. We have the resource standard rate is … Continue reading →

Posted in Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PRoject Management | Tagged , , , | Leave a comment

How to show separate costs for people and material in MS PROJECT 2013

  Hi, another question form my Blog Reader: “For a particular task, Can we get the material cost and labor cost separately for that particular day?, and can we display the material resources and work resources separately in the task … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , | Leave a comment

Resource over-allocation and Gantt chart in MS PROJECT 2013!

  Hi, one of my Blog readers ask me this: “Hello, could you please advice…you all seem to be very experienced with MS. ‘m interested in resource management. I tried to apply MSP and found that I’m not able to … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, PMI, PRoject Management | Tagged , , , | 9 Comments

Splitting Tasks again in MS PROJECT 2013

  Hi, I’ve got a question from one of my Blog Readers: “’I’m looking for a more precise method (non-graphical?) to set up the splits. For example I want to split a 10-work-day task halfway through, and have work resume … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , | 6 Comments

Task Calendars and Lag in MS PROJECT 2013

Hi, today I will answer to this question: “You have 2 tasks which own different task calendars (Standard 5day and 7day calendar). They are connected FS and have a lag, lets say 5 days. Which calendar does the lag use?” … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, PMI, PRoject Management | Tagged , , , | 5 Comments

Departments and Projects in MS PROJECT 2010 – Part 1

  Hi, today I am gong to show how are Departments connected with Projects in MS PROJECT SERVER 2010! First let me show you Departments in my Company: and than: and I will get: Now I am going to show … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project Server 2010, PMI, PRoject Management | Tagged , , | Leave a comment