Category Archives: Microsoft Project 2013
How to force Successor to start next working day in MS PROJET 2013
Hi, as usual, I’ve got a question from one of my Blog Reader: “If I have two tasks, the second task’s predecessor is the first task, and the first task ends on 7/10, I’d like the second task to … Continue reading
How to manage multiple Projects in MS PROJECT 2013
Hi, suppose that you have multiple Projects, and you do not have MS PROJECT SERVER. How can you see all Projects, Tasks, or Resources in MS PROJECT 2013? First what I’m going to do is to create Resource Pool: … Continue reading
Autolink inserted or moved Tasks in MS PROJECT 2013
Hi, if you are working with MS PROJECT 2013 (or 2010), you may want auto linking Tasks! First I’ll show you what’s happening if you do not turn on this feature. I will create 3 Tasks and I’ll link … Continue reading
Resource Pool and Tasks in MS PROJECT 2013
Hi, as usual, I have a question from one of my Blog readers. “Dear Nenad,Today it’s real tough for me to manage my projects (2010)hope you’ll find the solution for my head break1. my question is weather i can … Continue reading
Fiscal Year and MS PROJECT 2013
Hi, some of you told me that there is something wrong in MS PROJECT 2013 when displaying dates in Gantt Chart. Well, the solution is in Fiscal Year Settings. For some companies Fiscal Year is equal to Calendar Year (e.g. … Continue reading
Cost Resources and Actual value in MS PROJECT 2013
Hi, I have a question about Cost Resources and Actual value in MS PROJECT 2013: “Dear Nenad, I defined a cost resource “Hotel” and a work resource “Thomas” with hourly rate of 50 USD. For both of these resources … Continue reading
Resources and Over allocation in MS PROJECT 2013!
Hi, very often there is a question: “When is Resource over allocated, and how MS PROJECT 2013is dealing with it?” That is very easy to explain. First I will ad the three Tasks: and my Resource will be John … Continue reading
Effort and non effort driven Tasks in MS PROJECT 2013
Hi, here is the question from my Blog reader: “Nenad:Thanks very much for the posting! Do you know if there is any way of setting up a different default for this operation? More specifically, suppose that I have many … Continue reading
My arm is broken! :-(
Dear Blog Readers, Just an notice, that I broke my arm last Friday, so I will write my post a little bit “slower”! I hope that I will make a Post ‘till middle of the next week! Regards!
Resource Pool and Local Resources in MS PROJECT 2013
Hi, I have a question from one of my Blog readers: “Hello, Nenad. First, I’d like to thank you by your posts. They are very helpful. Now, to my question. I have a central team coordinating and working in … Continue reading