Category Archives: Microsoft Project 2013

Manually Scheduled Summary Tasks, and Subtasks in MS PROJECT 2013

Hi, Today I will explain how to use Manually Scheduled Summary Tasks and its Subtasks in MS PROJECT 2013 First I will create new Project, and then I will create one Manually Scheduled Summary Task, like in picture below: Now … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2010, PMI | Tagged , , , | 1 Comment

Maximal Units and Default Values in MS PROJECT 2013

Hi, my Blog Reader is in trouble. He wrote:”Hi Nenad, I am in need of a favor from you. I am currently working with the MS project to accomplish the team utilization and also to forecast the team’s availability. I … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 7 Comments

Multiple Critical Paths in MS PROJECT 2013

Hi, today I will show you how to use Option: Calculate multiple critical paths in MS PROJECT 2013! What is Critical Path indeed?  This is the longest path which show you how long will a Project Duration be. It is … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , | Leave a comment

Status Date line in MS Project 2013!

Hi, I’ve got a simple question from one of my Blog readers: “Hi, in your examples I can see Status Date in a Gantt Chart View. But I can not see it in my Projects. How to get this?” The … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 2 Comments

Split in progress Task option in MS PROJECT 2013!

Hi, My very good friend Ben Howard, find a problem, and a solution. I will share it with you. But before you continue to read this Post please taka a look on his great site: http://www.applepark.co.uk. Do I have to … Continue reading →

Posted in Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | Leave a comment

Duration with different Resources working time in MS PROJECT 2013!

Hi, with permission of my MVP friend Gérard Ducouret I will explain how different Resources working time affect Task duration in MS Project 2013! I will show you on the example. First, I will create (as I always do), the … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , | Leave a comment

Updating Project to status date versus Leveling in MS PROJECT 2013

Hi, yesterday I was teaching one of my Blog Readers about Leveling and Updating Projects in MS PROJECT 2013. The main problem was that after updating Project over allocated resources are still over allocated. I will explain the difference between … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , | 1 Comment

Critical Path in Timeline View with MS PROJECT 2013!

Hi, there is a question from one MS PROJECT user: “Hi! In the MS PROJECT 2013, is it possible to have the critical path displayed in the timeline View?” This Post will be short, because it is easy to do … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 5 Comments

Importing Resources from Excel into MS PROJECT 2013

Hi, my Blog reader has a problem: “Hi Nenad, I am Carlos Altamirano from Ecuador, South America. First of all I want to thank you very much for your always useful and concise work your are doing with your excellent … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , | 2 Comments

How to create graphic indicator for Task Status in MS PROJECT 2013

Hi, here is the question from one of my Blog Reader: “Hi Nenad, You are a lifesaver my friend 🙂 many thanks .., Another question, is there anyway I can color-code the various statuses ? so if LATE then show … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 2 Comments