Category Archives: MICROSOFT PROJECT

Extended duration when Successor has been started in MS PROJECT 2016

Hi, my Blog reader has a problem: “So what if we aren’t moving the project, just adding time to a task where a dependent task was able to start early. As an exampleTask A 10 daysTask B 2 daysTask C … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, PMI, PRoject Management | Tagged | Leave a comment

Material Resources with new Resource assigned to the Tasks in MS PROJECT 2016

Hi, today I’m going to show you what is going to happen with Material resources when you assign additional Work resources to the Task which has already started and have some actuals. I will use Microsoft Project 2016! First I’m … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, PMI, PRoject Management | Tagged | Leave a comment

Fixed Work and Manually scheduled Tasks in Microsoft Project 2016

Hi, I’ve got a question from one of my Blog Readers: “Dear Nenad, I have a problem with Fixed Work Task Type in MS PROJECT. When I add resource to a Fixed Work Task Type, and Task is Manually Scheduled, … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016 | Tagged , | Leave a comment

Baseline and deleted Tasks in MS PROJECT 2013, what if I do not have Inactive button?

Hi, my last Blog post is here: https://ntrajkovski.com/2015/09/22/baseline-and-deleted-tasks-in-ms-project-2013/ But, I have a question about that. That question is: “Hi Nenad, do all versions of project have the deactivate function? If not, is there a workaround? “ The answer is, older … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged | Leave a comment

Baseline and deleted Tasks in MS PROJECT 2013

Hi, I got a lot of questions about differences, for example, in Task Table when Project has Baseline, and The Task is deleted. I will show you what do in MS PROJECT 2013! First, I will crate very Simple Project: … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , | 3 Comments

Baseline and Calendars in MS PROJECT 2013

Hi, I got a question from my Blog Reader: “Dear Nenad, I have a problem. I set up Base Calendar with exceptions. I create a Schedule, assign Resources, and I save the Baseline. But after some time I notice that … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , | Leave a comment

Effort estimate in hours with MS PROJECT 2013

Hi, I’ve got a lot of questions like this one: “Hi, you have a lot of examples with estimating Durations! But we are estimate in hours. We don’t know Duration, but how many hours are needed to complete our Tasks! … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged | Leave a comment

how to edit Multiple Tasks at once in MS PROJECT 2013

Hi, often you will need to edit information not only for single, but for multiple Tasks in MS PROJECT 2013, and you will not want to edit Task by Task because it is time consuming. What can you do? First … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010 | Tagged | 2 Comments

Finish to Finish / Start to Start Dependencies with LAG in MS PROJECT 2013!

Hi, my Blog reader has a question: “Dear Nenad, can you explain Lag with Dependencies other than Finish to Start, like Finish to Finish and Start to Start?” I will show you how to do that in MS PROJECT 2013! … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged | 2 Comments

How to enable adding Columns in MS PROJECT 2013 Tables?

Hi, this will be a short one, but I need to help to one of my Blog Readers. The question is: “Dear Nenad, in MS PROJECT 2013, I can add additional Columns to some Tables, but not to all of … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged | Leave a comment