Resources and Durations – how are they linked in MS PROJECT 2013!
Hi, very good friend of mine has a problem: “Nenad, please help me. I want to have some Resources with different working hours (for Example, John 1 hour per day, Mary 2 hours per day), and when I assign Single … Continue reading
Adding new Resource on the Partial Finished Task in MS PROJECT 2013 – Part 2 of 2!
Hi, Today I’ll show another way of adding Resource after it is, for example, 40% Finished. first, I’ll show you pictures from my Previous Post, so I will create on simple Project in MS PROJECT 2013: and I will create … Continue reading
Adding new Resource on the Partial Finished Task in MS PROJECT 2013 – Part 1 of 2!
Hi, I had a very good question from one of my Blog Readers: “Hi Nenad. Can you tell me what is going to happen if I have one Resource on the Task, and that Task is finished, for example, 40%, … Continue reading
Strange Duration in MS PROJECT 2013 – Bug or Not!
Hi, I will show you something that makes MS PROJECT users crazy! Of course I’ll use MS PROJECT 2013. I will first, create a Brand new Project with one Task with 5 days Duration, like this: Everything is just fine. … Continue reading
24 Hours Calendar – how it works in MS PROJECT 2013
Hi, I have a lot of questions about MS PROJECT 2013 Calendars, especially about 24 hours Calendar. I will explain how does it work in MS PROJECT 2013. First I will Create a very Simple Project with only one Task … Continue reading
Material Resources and Calendars in MS PROJECT 2013 – where is the link?
Hi, as usual, I have a question from one of my Blog Readers: “Hi Nenad. i follow your blog step but i added resource as material not as work, but it doesn’t come up to me in the calendars list … Continue reading
Status field in MS PROJECT 2013
Hi, today I’ll show you how Status field works in MS PROJECT 2013. As usual I am going to Create some Tasks: I will add the Status field in the View: ¸ As you can see Task 1 is … Continue reading
Inactive Tasks in MS PROJECT 2013
Hi, this Post will be a really short one! I’m going to explain how Inactive Task is different in MS PROJECT 2013. First, notice that this functionality is available only with MS PROJECT 2013 PROFESSIONAL version. I’ll create new Project,first: … Continue reading
How to avoid adding column to Tables in MS PROJECT 2013
Hi, my Blog reader wants to disable Add New Column functionality in MS PROJECT 2013. It is very easy. First, I’ll create new Project: As you can see I’m viewing the Gantt Chart. In this chart I’m looking at the … Continue reading
How to make a right Schedule for your Project, after it begin in MS PROJECT 2013
Hi, in this post I will explain what to do with your Project when you are late, and how to make your schedule Accurate! First, I will create some Tasks in MS PROJECT 2013: Then some Resources: Finally I will … Continue reading