Remove Resource Pool from MS PROJECT 2013
Hi, again, a question from one of my Blog readers: “Hello Nenad, How does one remove a resource pool from a master project completely from MS Project 2013. I can’t keep other sub projects that formerly were connected to the … Continue reading
Multiple Critical Paths in MS PROJECT 2013
Hi, we all know what Critical Path means. It is path in which, if any Activity is late, the whole Project is late. Let me show you Critical Path in MS PROJECT 2013. First I’ll create new Project with some … Continue reading
Some additional setup in MS PROJECT 2013
Hi, first Blog Post in new 2014 year. I’ve been asked about some recommendations about additional setup in MS PROJECT 2013 There is a lot of setup which you can do in MS PROJECT 2013. You can set up … Continue reading
Collapsing the Ribbon in MS PROJECT 2013
Hi, this will be an easy one, because tomorrow is a New Year (2014), so I’ll finish this year with an answer to my Blog Reader. The Problem is very Simple: “Dear Sir, I’m using the Ribbon all the time, … Continue reading
Work Package versus Activity in MS PROJECT 2013
Hi, another question from one of my Blog Readers: “Hello; I have a question about “work package”. Is work package the same as “activity” or “activity” is more detailed than a work package? Thank you” Theory first. Suppose that … Continue reading
Generic Resources and different capacity in MS PROJECT 2013
Hi, again one interest question from my Blog reader: “Dear Nenad,Thank you VERY much for your very informative blog! I enjoy reading your posts and visit the site often. I would appreciate if you could answer my question regarding managing … Continue reading
Start and Finish Date with Auto Scheduled Task
Hi, first of all, apologies for delaying with my regular Post, but I was very busy with organizing SPCAdriatics (SharePoint and Project) conference last weeks (www.spcadriatics.com) Again, a question from one of my Blog readers: “Greetings Sir, Thanks kindly for … Continue reading
Lag in MS PROJECT 2013
Hi, these days I’m busy with organizing Conference (www.spcadriatics.com), btu I have a question form on of my Blog Readers, so I do not want to disappoint him. Here is the question: “This is very good information thank you. I … Continue reading
% Complete vs % Work Complete in MS PROJECT 2013
Hi, some people asked me about difference between %Complete, and %Work Complete. I’ll show you the difference with a very simple example in MS PROJECT 2013. First, I will create a Simple Project with a single Task: I will have … Continue reading
ASAP and ALAP constraint combination in MS PROJECT 2013
Hi, my Blog Reader has a problem: “Please can you help me. I would like to know how I can ask MS project to set one task ALAP without causing successors to move ALAP as well. In other words, I … Continue reading