-
Recent Posts
Archives
Categories
Tag Archives: Microsoft Project 2013
How to apply multiple Resource Calendars to the Same Resource in MS PROJECT 2013?
Hi, my Blog reader has a problem: “My problem is that some of resources have 2 work schedules. When they work on-shore (5 days week 8 hours day) and off-shore (7 days week and 11 hours day), For each … Continue reading
Baseline for Subprojects in MS PROJECT 2013
Hi, Today I’m going to explain how to set and see Baseline for Subprojects in MS PROJECT 2013, and how to see those Baselines in Master Project! First I’m going to create two Brand new Projects with one Task: and … Continue reading
How to Assign different Overtime Rate in MS PROJECT 2013
Hi, in one of my Posts I have explained how to calculate and work with Overtime hours in MS Project 2013, so I am not going to do it again. This time I will explain how to apply different … Continue reading
How to replace Generic resources with those with specific skills in MS PROJECT 2013
Hi, again my Blog Reade has a Problem. Here it is: “I have a challenging task to transition unorganized planning in my company to using ms project professional 2010 with share point site. We have generic resources like developers, testers … Continue reading
Work without Resources in MS PROJECT 2013! Is it possible?
Hi, again I have a question from my Blog Reader: “Can you advise me how to handle a closed task that has a resource assigned, but the resource will eventually spend 0 hours. So it is in fact a 100 … Continue reading
How to manage Projects with SharePoint 2013 and MS PROJECT Professional 2013 – Part 2
Hi! Here is Scenario! I want to Manage my Project in MS PROJECT PRO 2013! I want to upload an mpp file in SharePoint 2013, and there I want to have all my Project Documents, and I want to track … Continue reading
How to compare Projects in MS PROJECT 2013
Hi, in may cases you will have more than one Microsoft Project file for the same Project. Usually this is called versioning! And, after some time you will want to know where are the differences between two versions of your … Continue reading
Resource pool and subprojects in MS PROJECT 2013!
Hi, again one of my Blog readers has a problem: “I followed your instructions but I am running into a small issue. While my master project shows all the sub-projects and the attached resource pool in the resources sheet, when … Continue reading
Fixed Duration and effort driven Task in MS PROJECT 2013
Hi, My Blog Reader has a problem: “Just a question. When I assigned a task to Fixed Duration, WITH EFFORT DRIVEN I see that Project has calculated some of the resources to work 50% or 33%. How does that … Continue reading
Resource vs. Task Calendar in MS PROJECT 2013
Hi, another question from my Blog reader: “How do you determine whether to create a task calendar or a resource calendar?For example I start off with setting up the project calendar as standard, and then I decide that a particular … Continue reading