How to setup complex Graphical Indicators with MS PROJECT 2016
Hi, I can see on the forums that lot of MS PROJECT 2016 user have problem with graphical indicators. For example, they want to see Actual Work compared with base lined work, and see the status. OK, that is not … Continue reading
How to change Resource Assignments for Multiple Tasks in MS PROJECT 2016
Hi, Here is a problem that one of my Blog Readers have: “Is there a way to have the same resource – Team A work on multiple tasks and a place where I can change the “Units %” from 300% … Continue reading
Why is my Task Type changed from Non Effort Driven to Effort Driven automatically in MS PROJECT 2016
Hi I have a question from one of my Blog readers: “I wonder if this is a bug in MS Project 2016?Here what I did:1. Created a 3-day fixed units, non-effort-driven task2. Assigned one resource at 100% capacity3. Changed … Continue reading
Posted in Uncategorized
1 Comment
Extended Duration with Fixed working hours–MS PROJECT 2016
Hi, I have very interesting question from one of my Blog readers: “Hi Nenad, I would appreciate if you could advise on the following two topics: 1. How to handle the situation when a task is delayed due to some … Continue reading
Duration vs. Manually entered actual work in MS PROJECT 2016
Hi, I’ve got a question form one of my Blog readers: “Hi Nenad,Based on the example in your previous post please answer the following questions:1) When you manually updated the actual work in each of the 3 days for Resource … Continue reading
Actual Duration vs. Actual work in MS PROJECT 2016
Hi, I got a Business Case from my Blog Reader wit, of course, a problem. I will go step by step through it with MS PROJECT 2016! In Italic font is my blog reader Text 1. I created a … Continue reading
How to show Resource overallocation within one day in MS PROJECT 2016?
Hi, I have a question from one of my Blog Readers: “Hi,I have the following issue … I have a resource with an 8-hour working day. I assign him a task starting 9:00 am with a duration of 3 … Continue reading
Resource Calendar vs. Units in Microsoft Project 2016
Hi, I’ve got a very good question from one of my blog Readers: “Dear Nenad, Could you please help me with a question on resource calendar?If a resource is part time only work 3 days a week. I need to … Continue reading
How to change rates and costs without affecting past Tasks in MS PROJECT 2016?
Hi, I’ve got a question from one of my Blog Readers: “Hi!I am wondering how you would manage a rate increase in MS Project halfway through the project that is not retroactive. If I change the $/hr for a resource, … Continue reading
% Complete and Actual hours for particular Resource in MS PROJECT 2016
Hi, I got interesting question from one of my Blog Readers: “Nenad this is very helpful, however, how would you adjust the scenario where the Actual work by John (100%) and Tom (50%) who are two resources assigned to this … Continue reading