-
Recent Posts
Archives
Categories
Category Archives: Microsoft Project 2013
Duration and % completed–relation between them in MS PROJECT 2016
Hi, I noticed that lot of MS Project users have a problem with Duration and work which was already completed. Let me give you an example in MS PROJECT 2016. Let’s say that we have a one Task Project, with … Continue reading
Assign Resources to different time on the same Task in MS PROJECT 2016
Hi, one of my Blog readers has a questions: “One activity has 3 days Duration, and we need to assign 2 resources. First resource will work all 3 days on it, but second is only needed for 2nd day. How … Continue reading
Additional Resources assigning to the Task which have work in progress in MS PROJECT 2016
Hi, Today I’m going to explain what happens if I assign additional resource in Task which has a progress with MS PROJECT 2016. First, I’m going to create brand new Project: I have two resources available: I will assign John … Continue reading
Actual duration for manually entered actual work in MS PROJECT 2016
Hi, I have a question from my Blog reader, and I’m going to explain the problem step by step. Of course I will use MS PROJECT 2016! My blog reader’s problem is written with Italic. 1. Let’s create a 5 … Continue reading
Effort without specific Tasks in Projects using Microsoft Project 2016!
Hi, often I have a question like this: “How to assign Work to someone when that work is not to be linked with any specific Task?”. I will show you how with MS PROJECT 2016! But first I have to … Continue reading
Multiple relationships between Tasks–is this possible?
Hi, I have a great question form one of my Blog readers: “Hi Nenad, thanks for your time and experience. I have a question:I have to tasks 1 and 2.Task 2 starts with 1 day of delay of the start … Continue reading
Task Calendar and Resources – how they fit together in MS PRIJECT 2016?
Hi, I had a lot of question about the Topic I will write about today. Basically it is about relations between Resource (with no Calendar, or, to be more precise, which has Standard Calendar assigned), and specific Task with Specific … Continue reading
Baseline in Master and Sub-Projects with MS PROJECT 2016
Hi, we all know what the Baseline is. But where is the right place to make it, if we have a Project which is Subproject of Master Project. I will show you where with MS PROJECT 2016. First of all … Continue reading
Assignment Delay field in MS PROJECT 2016
Hi, in Microsoft Project 2016 there is one very useful field called: Assignment Delay. Let me show you how useful is it, and how can you use it. First, as I always do, I will create simple Project: I will … Continue reading
Project Summary Task and Calendars in Microsoft Project 2016
Hi, I have interesting question from my Blog reader: “How does one change the calendar for the Project Summary Task? The schedule is developed and has a calendar, other than the standard calendar, associated with all the tasks, but … Continue reading