Category Archives: Microsoft Project 2013
Placeholder field in MS PROJECT 2016
Hi, in MS PROJECT 2016, there is on, not so often used, field – Placeholder. Let me create new Project with three Tasks: As you can see, Task 1 and Task 2 are Manually scheduled, and Task 3 is Auto … Continue reading
Update the task as 100% without changing work hours automatically in MS PROJECT 2016 – is it possible?
Hi, I’ve got very good question from one of my Blog Readers: “How can I do to update the task as 100% but without changing work hours automatically? Because I want to know that my team is more efficient than … Continue reading
How to disconnect relation between %Complete and %Work complete in MS PROJECT 2016?
Hi, I have a question from one of my blog readers: “Hi,I just came across your resource tool and am hoping to find some help. I am having trouble disconnecting % Work Complete (Actual work done) from % Complete … Continue reading
Replacing Resources on partial done Tasks–Microsoft Project 2016
Hi, I have a question from my Blog reader: “Hi Nenad and thank you very much for your blog. I have a question for you. Suppose you have a 10d task with a generic resource assigned to it ( total … Continue reading
Resource rates and Billing rates in MS PROJECT 2016
Hi! I always get a question like this: “I need to charge an hourly rate per project. My hourly rate is $100.00 per hour. I have an employee work for me. Their rate is $20.00 per hour. I need to … Continue reading
%Complete, %Work Complete, and Project without Resources with MS PROJECT 2016!
Hi, I’ve got a question from one of my Blog Readers: “Please clarify the following: I have created a Sample project in MS Project 2013, with tasks and assigned duration with required predecessors.I have base lined the plan and started … Continue reading
New Tasks and saved Baseline in MS PRIOJECT 2016
Hi, I have a reader who is novice in MS PROJECT 2016, and he has a problem; “Hi, I hope you are in good health. I have some quires about cost tracking in MS Project. I had previously saved … Continue reading
Resource capacity in Hours with MS PROJECT 2016 – is it possible?
Hi, my Blog Reader has a question: “I have a project plan with certain milestones which are to be completed on specific dates and I have resources assigned. But as per plan, the resource allocation hours are reduced whereas in … Continue reading
Actual Duration, Actual work and Fixed work Tasks in MS PROJECT 2016
Hi, here is one problem that my Blog Reader has (I will go step by step, and I will use MS PROJECT 2016) “When multiple resources are assigned to the task, for a given Total Work we can calculates the … Continue reading
Effect of initial resource assignment on calculation of Individual resource’s work in MS PROJECT 2016
Hi, I’ve got very good question form one of my Blog readers: “The effect of initial resource assignment on calculation of Individual resource’s work. Suppose we want have two resources R1 (100%) and R2(50%) to work on a 20h fixed … Continue reading