Relation between Overtime and Duration in MS PROJECT 2016
Hi, I have a question from oen of my Blog readers: “Every time I allocate the whole work hours to overtime hours the Duration column turns into 0 and the start and finish dates and time are the same. Why?” … Continue reading
How to setup complex Graphical Indicators with MS PROJECT 2016
Hi, I can see on the forums that lot of MS PROJECT 2016 user have problem with graphical indicators. For example, they want to see Actual Work compared with base lined work, and see the status. OK, that is not … Continue reading
How to change Resource Assignments for Multiple Tasks in MS PROJECT 2016
Hi, Here is a problem that one of my Blog Readers have: “Is there a way to have the same resource – Team A work on multiple tasks and a place where I can change the “Units %” from 300% … Continue reading
Extended Duration with Fixed working hours–MS PROJECT 2016
Hi, I have very interesting question from one of my Blog readers: “Hi Nenad, I would appreciate if you could advise on the following two topics: 1. How to handle the situation when a task is delayed due to some … Continue reading
Actual Duration vs. Actual work in MS PROJECT 2016
Hi, I got a Business Case from my Blog Reader wit, of course, a problem. I will go step by step through it with MS PROJECT 2016! In Italic font is my blog reader Text 1. I created a … Continue reading
Resource Calendar vs. Units in Microsoft Project 2016
Hi, I’ve got a very good question from one of my blog Readers: “Dear Nenad, Could you please help me with a question on resource calendar?If a resource is part time only work 3 days a week. I need to … Continue reading
How to change rates and costs without affecting past Tasks in MS PROJECT 2016?
Hi, I’ve got a question from one of my Blog Readers: “Hi!I am wondering how you would manage a rate increase in MS Project halfway through the project that is not retroactive. If I change the $/hr for a resource, … Continue reading
% Complete and Actual hours for particular Resource in MS PROJECT 2016
Hi, I got interesting question from one of my Blog Readers: “Nenad this is very helpful, however, how would you adjust the scenario where the Actual work by John (100%) and Tom (50%) who are two resources assigned to this … Continue reading
Milestone and Finish to Finish relationship in MS PROJECT 2016
Hi, I’ve got an interesting question form one of my blog reader. He’s got a problem. I will show you what kind of Problem does he has with MS PROJECT 2016! Firs I will create new Project: Everything looks perfect. … Continue reading
Importing Resources from Excel into MS PROJECT 2013 and PROJECT 2016–VIDEO IS HERE!
I’m proudly announce that Webucator (www.webucator.com) recorder the Video https://www.youtube.com/watch?v=mniDdkKxgpM&feature=youtu.be of my Blog Post which you can Find here: https://ntrajkovski.com/2015/02/27/importing-resources-from-excel-into-ms-project-2013/. If you want learn a lot about MS PROJECT, I strongly recommend that you visit their site https://www.webucator.com/microsoft-training/project.cfm, and you … Continue reading