Category Archives: MICROSOFT PROJECT
How to change Resource Assignments for Multiple Tasks in MS PROJECT 2016
Hi, Here is a problem that one of my Blog Readers have: “Is there a way to have the same resource – Team A work on multiple tasks and a place where I can change the “Units %” from 300% … Continue reading
Extended Duration with Fixed working hours–MS PROJECT 2016
Hi, I have very interesting question from one of my Blog readers: “Hi Nenad, I would appreciate if you could advise on the following two topics: 1. How to handle the situation when a task is delayed due to some … Continue reading
Duration vs. Manually entered actual work in MS PROJECT 2016
Hi, I’ve got a question form one of my Blog readers: “Hi Nenad,Based on the example in your previous post please answer the following questions:1) When you manually updated the actual work in each of the 3 days for Resource … Continue reading
How to show Resource overallocation within one day in MS PROJECT 2016?
Hi, I have a question from one of my Blog Readers: “Hi,I have the following issue … I have a resource with an 8-hour working day. I assign him a task starting 9:00 am with a duration of 3 … Continue reading
Resource Calendar vs. Units in Microsoft Project 2016
Hi, I’ve got a very good question from one of my blog Readers: “Dear Nenad, Could you please help me with a question on resource calendar?If a resource is part time only work 3 days a week. I need to … Continue reading
How to change rates and costs without affecting past Tasks in MS PROJECT 2016?
Hi, I’ve got a question from one of my Blog Readers: “Hi!I am wondering how you would manage a rate increase in MS Project halfway through the project that is not retroactive. If I change the $/hr for a resource, … Continue reading
% Complete and Actual hours for particular Resource in MS PROJECT 2016
Hi, I got interesting question from one of my Blog Readers: “Nenad this is very helpful, however, how would you adjust the scenario where the Actual work by John (100%) and Tom (50%) who are two resources assigned to this … Continue reading
Milestone and Finish to Finish relationship in MS PROJECT 2016
Hi, I’ve got an interesting question form one of my blog reader. He’s got a problem. I will show you what kind of Problem does he has with MS PROJECT 2016! Firs I will create new Project: Everything looks perfect. … Continue reading
Is it possible to make a Project plan without Project Start Date in MS Project 2016!
Hi, I’ve got very interesting question from one of my blog readers: “Is it possible to create project plan without Start date, and the let MS PROJECT 2016 to calculate finish like t0 + ndays?” I will show you … Continue reading
Task type and Resource Calendars in MS PROJECT 2016
Hi, I’ve got very specific question from one of my blog Reader, and I’m going to answer this step by step using MS PROJECT 2016 Here is Scenario from my Blog Reader (Italic font represent his questions, and Normal font represent … Continue reading