Category Archives: PRoject Management

Duration vs. Manually entered actual work in MS PROJECT 2016

Hi, I’ve got a question form one of my Blog readers: “Hi Nenad,Based on the example in your previous post please answer the following questions:1) When you manually updated the actual work in each of the 3 days for Resource … Continue reading →

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 2 Comments

Actual Duration vs. Actual work in MS PROJECT 2016

  Hi, I got a Business Case from my Blog Reader wit, of course, a problem. I will go step by step through it with MS PROJECT 2016! In Italic font is my blog reader Text 1. I created a … Continue reading →

Posted in Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , | 1 Comment

How to show Resource overallocation within one day in MS PROJECT 2016?

  Hi, I have a question from one of my Blog Readers: “Hi,I have the following issue … I have a resource with an 8-hour working day. I assign him a task starting 9:00 am with a duration of 3 … Continue reading →

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

Resource Calendar vs. Units in Microsoft Project 2016

Hi, I’ve got a very good question from one of my blog Readers: “Dear Nenad, Could you please help me with a question on resource calendar?If a resource is part time only work 3 days a week. I need to … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

How to change rates and costs without affecting past Tasks in MS PROJECT 2016?

Hi, I’ve got a question from one of my Blog Readers: “Hi!I am wondering how you would manage a rate increase in MS Project halfway through the project that is not retroactive. If I change the $/hr for a resource, … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

% Complete and Actual hours for particular Resource in MS PROJECT 2016

Hi, I got interesting question from one of my Blog Readers: “Nenad this is very helpful, however, how would you adjust the scenario where the Actual work by John (100%) and Tom (50%) who are two resources assigned to this … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, PMI, PRoject Management | Tagged , , | 2 Comments

Milestone and Finish to Finish relationship in MS PROJECT 2016

Hi, I’ve got an interesting question form one of my blog reader. He’s got a problem. I will show you what kind of Problem does he has with MS PROJECT 2016! Firs I will create new Project: Everything looks perfect. … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Is it possible to make a Project plan without Project Start Date in MS Project 2016!

  Hi, I’ve got very interesting question from one of my blog readers: “Is it possible to create project plan without Start date, and the let MS PROJECT 2016 to calculate finish like t0 + ndays?” I will show you … Continue reading →

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 1 Comment

Task type and Resource Calendars in MS PROJECT 2016

Hi, I’ve got very specific question from one of my blog Reader, and I’m going to answer this step by step using MS PROJECT 2016 Here is Scenario from my Blog Reader (Italic font represent his questions, and Normal font represent … Continue reading →

Posted in MICROSOFT PROJECT, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Resource calendar vs. Task Calendar, and weekends in MDS PROJECT 2016

Hi, Again, I have a question from one of my Blog readers, which is related to my previous post: “Hi Nenad,¸ Thank you very mush. But can you please explain the following inconsistency in MSP behavior: If in the example … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , | 4 Comments