-
Recent Posts
Archives
Categories
Tag Archives: Micorosft Project 2016 – Schedule
Recording task progress ahead of schedule in MS PROJECT 2016
Hi, today I am going to clarify one important thing which bothers a lot of of my Blog readers. I will go step by step through example and explain them. First I’m going to build simple Project: Now I will … Continue reading
Posted in MS PROJECT 2016, PMI, PRoject Management
Tagged Micorosft Project 2016, Micorosft Project 2016 - Schedule
1 Comment
Calculate Variance in Working Days after setting another baseline in MS PROJECT 2016
Hi, I’ve got a question which is: “How do you calculate the working days in formulas when the baseline is not Baseline 0, and you need to see variance of that Baseline?” It’s easy and I’ll show you how with … Continue reading
Posted in MS PROJECT 2016, PMI, PRoject Management
Tagged Micorosft Project 2016, Micorosft Project 2016 - Schedule
1 Comment
Customized resource calendar and its effect on task duration in MS PROJECT 2016!
Hi, my blog reader has a question and I’m going to repro his scenario step by step, and answer the question using MS PROJECT 2016. First I will create a 5 day Task: There are 2 resources assigned to the … Continue reading
Fixed Duration Tasks and Resource availability in MS PROJECT 2016
Hi, today I will show you what happens wen you have Fixed Duration Tasks with Resources assigned to them, and those resource are unavailable at the specific time. I will use MS PROJECT 2016 First I will create simple Project … Continue reading
Predecessors, Successors and Task form in MS PROJECT 2016
Hi, How often do you have a large Project with lot of Tasks? Hundreds of them. And your schedule is very complicated. And then, suddenly you have to change something. Maybe relations within Tasks, maybe your timeline is too long, … Continue reading
Project management Task and Administrative work in MS PROJECT 2016
Hi, my blog reader has a question about Project management Task, and administrative work, and how to handle it in MS PROJECT 2016? Here is Scenario. This is Project Schedule: First of all, I will advice not to use Project … Continue reading
Fixed work Task Type with limited Resource availability in MS PROJECT 2016!
Hi, my Blog reader run into problem with limited Resource availability. I will show the scenario and explain it with MS PROJECT 2016. I will create simple Project with one Task, 4 day duration, and I will assign John to … Continue reading
How to “loan” Resources from non-critical to critical Tasks in MS PROJECT 2016
Hi, today I will explain one specific Case which one of my Blog users have. And I will do it by reproducing this Case step-by-step, using MS PROJECT 2016! There are three tasks with resources assigned to them: I will … Continue reading
Costs for no work done in MS PROJECT 2016
Hi, again my Blog reader has a problem, which is: “I have a question. Let’s say I have 4 hours of delay against a project as “ALL RESOURCES” had to wait for a crane to arrive before work could commence. … Continue reading
Assign Resources to different time on the same Task in MS PROJECT 2016
Hi, one of my Blog readers has a questions: “One activity has 3 days Duration, and we need to assign 2 resources. First resource will work all 3 days on it, but second is only needed for 2nd day. How … Continue reading