Move vs Update Tasks in MS PROJECT 2016
Hi, in my last post I wrote about differences between Move and Update options in MS PROJECT 2016 on the Project Level, Now it is time to explain those two different options on the Task level. First, I will create … Continue reading
Move vs Update Project in MS PROJECT 2016
Hi, as a first post for this year I will answer to the question from my Blog reader: “Please advise on when to use Move vs Update Project to reschedule incomplete tasks after a specified date?” There is a huge … Continue reading
% Work Completed without Resources assigned to Tasks
Hi, I wrote several Posts about % Work completed field, and how does it change when assigned Resources to the Task. As you know, Work is 0 hours until you assign Resource to the Task. But, is it possible … Continue reading
Different weekends for Resources in MS PROJECT 2016
Hi, I have a very good question from one of my Blog Readers: “Hi! How does one fix different holidays for persons on the same activity? That is if X and Y are working on the same Project and Task … Continue reading
Milestone with “Finish not later than” constraint and Float Ii n MS PROJECT 2016!
Hi guys, I have another great question from one of my Blog readers: “Hi Nenad, I have another question for you.Suppose you have a task with start date, for example, 7 Nov and 5d duration. Its successor is a finish … Continue reading
Fixed duration Tasks and over allocation resolution in MS PROJECT 2016
Hi, I have interesting question form one of my Blog Readers: “I have below query in Fixed Duration Task.Step1: created a task “paint the wall” with duration as 10 days (work starts by a Monday). Task is fixed durationStep2: created … Continue reading
How to disconnect relation between %Complete and %Work complete in MS PROJECT 2016?
Hi, I have a question from one of my blog readers: “Hi,I just came across your resource tool and am hoping to find some help. I am having trouble disconnecting % Work Complete (Actual work done) from % Complete … Continue reading
Replacing Resources on partial done Tasks–Microsoft Project 2016
Hi, I have a question from my Blog reader: “Hi Nenad and thank you very much for your blog. I have a question for you. Suppose you have a 10d task with a generic resource assigned to it ( total … Continue reading
Some leveling options in Microsoft Project 2016
Hi, my Blog reader has a question: “Would you please give an example with “Leveling Can Adjust Individual Assignments on a Task” and an other example with “Level Resources with the Proposed Booking Type” in MS Project 2016 resource leveling … Continue reading
Resource rates and Billing rates in MS PROJECT 2016
Hi! I always get a question like this: “I need to charge an hourly rate per project. My hourly rate is $100.00 per hour. I have an employee work for me. Their rate is $20.00 per hour. I need to … Continue reading