Custom duration and date fields in MS PROJECT 2013

Here is a question form one of my Blog Readers: “I have another possible bug in MSP 2013. Try this oneInsert Date1, Insert Duration1, Insert Date2. Now go to custom fields and make date2 a formula [(date1)+(duration1). The obvious answer … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 4 Comments

Cancelling Project when using Resource Pool in MS PROJECT 2013! – The easiest way

Hi, I will repeat a lot of Pictures from my previous Post, and I’ll show you how to break the Link between a Project, and Resource Pool.. I will show you a case in MS PROJECT 2013! First, as usual … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013 | Tagged , , , , | 4 Comments

Scheduled Duration, Start and Finished Date in MS PROJECT 2013

Hi, A question from my Blog reader is: “Please clarify the purpose  of fields Schedule Duration, Schedule Start & Schedule Finish. In which context they are used and how they differ from Duration, Start & Finish Fields ?” I will … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , , | Leave a comment

Reordering Tasks in Master Project with MICROSOFT PROJECT 2013!

Hi, again one of my Blog Readers has a question: “What if I want to make changes to the master project but don’t want it to change the sub projects? I want to be able to re-order the tasks in … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI | Tagged , , , | 2 Comments

A Small issue with Team Planner and Resource Leveling in MS PROJECT 2013

This will be a short one. Again, my fellow MPV Eric Uyttewaal found a Bug in MS PROJECT 2013. I will Crete two Tasks in MS PROJECT 2013: and one Resource: Finally I’ll assign this Resources to both Tasks: As … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI | Tagged , , | 2 Comments

Multiple Resource Pools in Subprojects in MS PROJECT 2013!

Hi, I have a question from on of my Blog Readers: “Is it possible to use separate Resource to Projects, and then to see all Resources in one Master Project?” The answer is: “YES” How? I’ll show you in MS … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 2 Comments

Bug with Inactive Tasks in MS PROJECT 2013!

Hi, My MVP Fellow, Dale Howard found this Bug in MS PROJECT 2013! I will Create brand new Project with some Tasks: Now, suppose that I want to make First four Tasks inactive: I will get: So far so good. … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | Leave a comment

Bug in Tracking Gantt View in MS PROJECT 2013

Hi, here is another small bug in MS PROJECT 2013. I will Create few Tasks in MS PROJECT 2013: I want to see Critical Path, so I’m going to Use Tracking Gantt View: and I’ll get: On the Right side … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 4 Comments

BUG Resource-related Cost field not recalculated in MS PROJECT 2013

Hi, here is minor bug in MS PROJECT 2013, found by Eric Uyttewaal, my MVP friend. First I am going to create New Project with Single Task (1 day duration): I will now Create two Resources: Ted and Fred: Yu … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 2 Comments

How to replace Resource for the partial completed Tasks in MS PROJECT 2013?

Hi, I’ve got a question from one of my Blog Readers: “Dear Nenad, I have the following scenario: I have A Task assigned with one Resource. He did 50% work, and then he left the Company. I must assign another … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 2 Comments