Category Archives: MICROSOFT PROJECT

Placeholder field in MS PROJECT 2016

Hi, in MS PROJECT 2016, there is on, not so often used, field – Placeholder. Let me create new Project with three Tasks: As you can see, Task 1 and Task 2 are Manually scheduled, and Task 3 is Auto … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Status Indicator in MS PROJECT 2016

Hi, there are some fields in MS PROJECT 2016, which are very useful but not so often used. One of them is Status indicator. What does it work? I will explain it in a simple example. First I will create … Continue reading →

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 2 Comments

Update the task as 100% without changing work hours automatically in MS PROJECT 2016 – is it possible?

Hi, I’ve got very good question from one of my Blog Readers: “How can I do to update the task as 100% but without changing work hours automatically? Because I want to know that my team is more efficient than … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, MS PROJECT 2016 | Tagged , , | Leave a comment

Units field in Resource assignment – MS PROJECT 2016

Hi, I’ve got a question from one of my Blog readers: “Max units field in Assign Resources are always in %? I want to use QTY instead of %, like we have 10 cranes available, and how many cranes are … Continue reading →

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Move vs Update Tasks in MS PROJECT 2016

Hi, in my last post I wrote about differences between Move and Update options in MS PROJECT 2016 on the Project Level, Now it is time to explain those two different options on the Task level. First, I will create … Continue reading →

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

How to make week shifts in MS PROJECT 2016?

Hi, Today, I will explain next Scenario in MS PROJECT 2016: Suppose that you have a project team who will work 5 days a week (Monday to Friday), but every third week the whole team will be off. This is … Continue reading →

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, PMI, PRoject Management | Tagged , , , , | Leave a comment

When to use Resource Calendars in MS PROJECT 2016

Hi, after my Post “Different weekends for Resources in MS PROJECT 2016”, there was a lot of discussion, that a problem can be solved with Resource Calendars, and that be will be the best way. Yes, it can be done … Continue reading →

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 1 Comment

% Work Completed without Resources assigned to Tasks

  Hi, I wrote several Posts about % Work completed field, and how does it change when assigned Resources to the Task. As you know, Work is 0 hours until you assign Resource to the Task. But, is it possible … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft Project Server 2010, MS PROJECT 2016 | Tagged , , | Leave a comment

Different weekends for Resources in MS PROJECT 2016

Hi, I have a very good question from one of my Blog Readers: “Hi! How does one fix different holidays for persons on the same activity? That is if X and Y are working on the same Project and Task … Continue reading →

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Milestone with “Finish not later than” constraint and Float Ii n MS PROJECT 2016!

Hi guys, I have another great question from one of my Blog readers: “Hi Nenad, I have another question for you.Suppose you have a task with start date, for example, 7 Nov and 5d duration. Its successor is a finish … Continue reading →

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment