Fixed duration Tasks and over allocation resolution in MS PROJECT 2016
Hi, I have interesting question form one of my Blog Readers: “I have below query in Fixed Duration Task.Step1: created a task “paint the wall” with duration as 10 days (work starts by a Monday). Task is fixed durationStep2: created … Continue reading
Replacing Resources on partial done Tasks–Microsoft Project 2016
Hi, I have a question from my Blog reader: “Hi Nenad and thank you very much for your blog. I have a question for you. Suppose you have a 10d task with a generic resource assigned to it ( total … Continue reading
%Complete vs. %Work Complete in MS PROJECT 2016!–when to use what?
Hi, very often I have questions like this one: Dear Nenad, I am going to develop a scheduled for a petrochemical plant shutdown project. My question is: “What percent complete should i use (% Complete or Work % Complete) … Continue reading
%Complete, %Work Complete, and Project without Resources with MS PROJECT 2016!
Hi, I’ve got a question from one of my Blog Readers: “Please clarify the following: I have created a Sample project in MS Project 2013, with tasks and assigned duration with required predecessors.I have base lined the plan and started … Continue reading
Resource capacity in Hours with MS PROJECT 2016 – is it possible?
Hi, my Blog Reader has a question: “I have a project plan with certain milestones which are to be completed on specific dates and I have resources assigned. But as per plan, the resource allocation hours are reduced whereas in … Continue reading
Actual Duration, Actual work and Fixed work Tasks in MS PROJECT 2016
Hi, here is one problem that my Blog Reader has (I will go step by step, and I will use MS PROJECT 2016) “When multiple resources are assigned to the task, for a given Total Work we can calculates the … Continue reading
Effect of initial resource assignment on calculation of Individual resource’s work in MS PROJECT 2016
Hi, I’ve got very good question form one of my Blog readers: “The effect of initial resource assignment on calculation of Individual resource’s work. Suppose we want have two resources R1 (100%) and R2(50%) to work on a 20h fixed … Continue reading
Relation between Overtime and Duration in MS PROJECT 2016
Hi, I have a question from oen of my Blog readers: “Every time I allocate the whole work hours to overtime hours the Duration column turns into 0 and the start and finish dates and time are the same. Why?” … Continue reading
Extended Duration with Fixed working hours–MS PROJECT 2016
Hi, I have very interesting question from one of my Blog readers: “Hi Nenad, I would appreciate if you could advise on the following two topics: 1. How to handle the situation when a task is delayed due to some … Continue reading
% Complete and Actual hours for particular Resource in MS PROJECT 2016
Hi, I got interesting question from one of my Blog Readers: “Nenad this is very helpful, however, how would you adjust the scenario where the Actual work by John (100%) and Tom (50%) who are two resources assigned to this … Continue reading