Work Package versus Activity in MS PROJECT 2013
Hi, another question from one of my Blog Readers: “Hello; I have a question about “work package”. Is work package the same as “activity” or “activity” is more detailed than a work package? Thank you” Theory first. Suppose that … Continue reading
Generic Resources and different capacity in MS PROJECT 2013
Hi, again one interest question from my Blog reader: “Dear Nenad,Thank you VERY much for your very informative blog! I enjoy reading your posts and visit the site often. I would appreciate if you could answer my question regarding managing … Continue reading
Start and Finish Date with Auto Scheduled Task
Hi, first of all, apologies for delaying with my regular Post, but I was very busy with organizing SPCAdriatics (SharePoint and Project) conference last weeks (www.spcadriatics.com) Again, a question from one of my Blog readers: “Greetings Sir, Thanks kindly for … Continue reading
Lag in MS PROJECT 2013
Hi, these days I’m busy with organizing Conference (www.spcadriatics.com), btu I have a question form on of my Blog Readers, so I do not want to disappoint him. Here is the question: “This is very good information thank you. I … Continue reading
Recurring week exceptions in MS PROJECT 2013
Hi, Suppose that you are working on the Project! And suppose that you have one week Vacation for whole company resources, each and every Year. How to make it in MS PROJECT 2013. First I’ll create a Project With one … Continue reading
% Complete VS Physical % Complete in MS PROJECT 2013
Hi, I will explain hot to track Physical % Complete in MS PROJECT 2013. In MS PROJECT you can Track %Complete, % Work Complete, and Physical % Complete. Where are the differences? % Complete is about Duration % Work Complete … Continue reading
Percentage completed vs. Actual Work in MS PROJECT 2013!
Hi, again, my Blog reader has a problem: “Dear Nenad, your blog is a real treasure and I am so happy I came across it a year ago when we started with the implementation of the MS Project Server 2010 … Continue reading
Baseline for Subprojects in MS PROJECT 2013
Hi, Today I’m going to explain how to set and see Baseline for Subprojects in MS PROJECT 2013, and how to see those Baselines in Master Project! First I’m going to create two Brand new Projects with one Task: and … Continue reading
How to manage multiple Projects in MS PROJECT 2013
Hi, suppose that you have multiple Projects, and you do not have MS PROJECT SERVER. How can you see all Projects, Tasks, or Resources in MS PROJECT 2013? First what I’m going to do is to create Resource Pool: … Continue reading
Fiscal Year and MS PROJECT 2013
Hi, some of you told me that there is something wrong in MS PROJECT 2013 when displaying dates in Gantt Chart. Well, the solution is in Fiscal Year Settings. For some companies Fiscal Year is equal to Calendar Year (e.g. … Continue reading