Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!

A Small issue with Team Planner and Resource Leveling in MS PROJECT 2013

This will be a short one. Again, my fellow MPV Eric Uyttewaal found a Bug in MS PROJECT 2013. I will Crete two Tasks in MS PROJECT 2013: and one Resource: Finally I’ll assign this Resources to both Tasks: As … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI | Tagged , , | 2 Comments

Multiple Resource Pools in Subprojects in MS PROJECT 2013!

Hi, I have a question from on of my Blog Readers: “Is it possible to use separate Resource to Projects, and then to see all Resources in one Master Project?” The answer is: “YES” How? I’ll show you in MS … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 2 Comments

Bug with Inactive Tasks in MS PROJECT 2013!

Hi, My MVP Fellow, Dale Howard found this Bug in MS PROJECT 2013! I will Create brand new Project with some Tasks: Now, suppose that I want to make First four Tasks inactive: I will get: So far so good. … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | Leave a comment

Bug in Tracking Gantt View in MS PROJECT 2013

Hi, here is another small bug in MS PROJECT 2013. I will Create few Tasks in MS PROJECT 2013: I want to see Critical Path, so I’m going to Use Tracking Gantt View: and I’ll get: On the Right side … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 4 Comments

BUG Resource-related Cost field not recalculated in MS PROJECT 2013

Hi, here is minor bug in MS PROJECT 2013, found by Eric Uyttewaal, my MVP friend. First I am going to create New Project with Single Task (1 day duration): I will now Create two Resources: Ted and Fred: Yu … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 2 Comments

How to replace Resource for the partial completed Tasks in MS PROJECT 2013?

Hi, I’ve got a question from one of my Blog Readers: “Dear Nenad, I have the following scenario: I have A Task assigned with one Resource. He did 50% work, and then he left the Company. I must assign another … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 2 Comments

Fixed Duration, actual work, remaining work – how are they linked in MS PROJECT 2013?

Hi, Today I’ll show you something that looks like a bug but it is not. Suppose that you have a Task with 5 days duration, and the Task Type is Fixed duration. I’ll do that Scenario in MS PROJECT 2013! … Continue reading

Posted in Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010 | Tagged , , , , , | 2 Comments

The Resume fields in MS PROJECT 2013

Hi, Imagine this situation: you have a Task with one Resource, and duration is 5 days. The task is on Track, and it is 50% completed. Suddenly, Resource get sick, and will be able to continue with work after few … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | Leave a comment

% Complete vs. Finish Date in MS PROJECT 2013

Hi, here is another problem from one of my Blog readers: “Hi Nenad – allow me to give you an example of my problem. A task with a finish date of May 5/14 has a % complete of 25%. When … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 8 Comments

Resources and Durations – how are they linked in MS PROJECT 2013!

Hi, very good friend of mine has a problem: “Nenad, please help me. I want to have some Resources with different working hours (for Example, John 1 hour per day, Mary 2 hours per day), and when I assign Single … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , , | 2 Comments