Update the task as 100% without changing work hours automatically in MS PROJECT 2016 – is it possible?
Hi, I’ve got very good question from one of my Blog Readers: “How can I do to update the task as 100% but without changing work hours automatically? Because I want to know that my team is more efficient than … Continue reading
Task Calendar in MS PROJECT 2016 – the right way to use it
Hi, as we all know, there are three types of Calendars in MS PROJECT 2016: Base Calendars, Resource Calendars and Task Calendars. they are prioritized in that order (from low to high importance), which means that Task Calendar has the … Continue reading
Move vs Update Project in MS PROJECT 2016
Hi, as a first post for this year I will answer to the question from my Blog reader: “Please advise on when to use Move vs Update Project to reschedule incomplete tasks after a specified date?” There is a huge … Continue reading
How to make week shifts in MS PROJECT 2016?
Hi, Today, I will explain next Scenario in MS PROJECT 2016: Suppose that you have a project team who will work 5 days a week (Monday to Friday), but every third week the whole team will be off. This is … Continue reading
When to use Resource Calendars in MS PROJECT 2016
Hi, after my Post “Different weekends for Resources in MS PROJECT 2016”, there was a lot of discussion, that a problem can be solved with Resource Calendars, and that be will be the best way. Yes, it can be done … Continue reading
Fixed duration Tasks and over allocation resolution in MS PROJECT 2016
Hi, I have interesting question form one of my Blog Readers: “I have below query in Fixed Duration Task.Step1: created a task “paint the wall” with duration as 10 days (work starts by a Monday). Task is fixed durationStep2: created … Continue reading
How to put different Overtime Work to Task in MS PROJECT 2016!
Hi, I have a very interesting question from one of my Blog Readers: “Hi Nenad, I want to put different overtime Work for a Task and Resources. Let’s say that I have Task1, and John an Mary are assigned to … Continue reading
New Tasks and saved Baseline in MS PRIOJECT 2016
Hi, I have a reader who is novice in MS PROJECT 2016, and he has a problem; “Hi, I hope you are in good health. I have some quires about cost tracking in MS Project. I had previously saved … Continue reading
How to show Resource overallocation within one day in MS PROJECT 2016?
Hi, I have a question from one of my Blog Readers: “Hi,I have the following issue … I have a resource with an 8-hour working day. I assign him a task starting 9:00 am with a duration of 3 … Continue reading
How to change rates and costs without affecting past Tasks in MS PROJECT 2016?
Hi, I’ve got a question from one of my Blog Readers: “Hi!I am wondering how you would manage a rate increase in MS Project halfway through the project that is not retroactive. If I change the $/hr for a resource, … Continue reading