How to create graphic indicator for Task Status in MS PROJECT 2013
Hi, here is the question from one of my Blog Reader: “Hi Nenad, You are a lifesaver my friend 🙂 many thanks .., Another question, is there anyway I can color-code the various statuses ? so if LATE then show … Continue reading
Reschedule uncompleted work and SNET constraint in MS PROJECT 2013
Hi, I have a question form my Blog Reader: “Hi NenadI have the issue. My tasks are all set to automatically scheduled. I update actuals weekly and once completed I update the project and select ‘reschedule uncompleted work to start … Continue reading
Lead time in relative Terms with MS PROJECT 2013
Hi, Lead is time which allow Successor Task to start before Predecessor is finished, and still keep Finish To Start relationship. I wrote about that in my Blog Post: https://ntrajkovski.com/2011/04/12/scheduling-problems-in-ms-project-2010-part-2/ Let’s see how to make it relative in MS PROJECT … Continue reading
How to set Resources to work at different time with different amount of work at the same Task in MS PROJECT 2013
Hi, I have a question from one of my Blog Readers: “” “Nenad, I have two Resources on the same Task. I want to assign them at different time and different work. Let’s say that John will work 40 hours … Continue reading
Multinational Calendars and how to use them in MS PROJECT 2013?
Hi, again, I have a question from one of my Blog readers: “Okay I have a question not certain if it belongs in this thread. I’m managing a project for resources in multiple locations using MS Project 2007: US and … Continue reading
Duration, Units, Work and Schedule in MS PROJECT 2013. How are they linked, and some tips and tricks!
Hi, this is my first Post in this year and it will be a quite long. Again, one of my Blog readers ha a problem, and this problem is about scheduling. Here it is: “Dear Nenad,Glad to find your site … Continue reading
Slack and Microsoft Project 2013
Hi, again my Blog reader has a problem: “Hi,I have a question about Slack, I am preparing a construction schedule for my small project and using M.S.P. the problem I have is, when I active the slack on the schedule, … Continue reading
Rescheduling Project or Tasks, and Constraints in MS PROJECT 2013
Hi, my Blog reader ha a question: “Dear Nenad, After we update the progress (% Complete) on various tasks on a baselined project, I understand we need to re-schedule the uncompleted work to start after the status date. This is … Continue reading
How to Move Project when Project has Manually Scheduled Tasks and/or Constraints in MS PROJECT 2013
Hi, I’ll how you how to move Project when it has Manually Scheduled Tasks or Constraints in MS PROJECT 2013 First I will make a simple Project with no manually Scheduled Tasks or Constraints. Now suppose that your plan is … Continue reading
Status date in “what if” scenario, or how to make our Projects actual data up to date in MS PROJECT 2013
Hi, my Blog reader has a “problem”: “Nenad, thank you for replay! Ok, my be I wasn’t clear with my question… Let me explain my self one more time. Perhaps I’m working on some project, it has 28 task with … Continue reading