Category Archives: MS PROJECT 2010
Bug in Tracking Gantt View in MS PROJECT 2013
Hi, here is another small bug in MS PROJECT 2013. I will Create few Tasks in MS PROJECT 2013: I want to see Critical Path, so I’m going to Use Tracking Gantt View: and I’ll get: On the Right side … Continue reading
BUG Resource-related Cost field not recalculated in MS PROJECT 2013
Hi, here is minor bug in MS PROJECT 2013, found by Eric Uyttewaal, my MVP friend. First I am going to create New Project with Single Task (1 day duration): I will now Create two Resources: Ted and Fred: Yu … Continue reading
How to replace Resource for the partial completed Tasks in MS PROJECT 2013?
Hi, I’ve got a question from one of my Blog Readers: “Dear Nenad, I have the following scenario: I have A Task assigned with one Resource. He did 50% work, and then he left the Company. I must assign another … Continue reading
Fixed Duration, actual work, remaining work – how are they linked in MS PROJECT 2013?
Hi, Today I’ll show you something that looks like a bug but it is not. Suppose that you have a Task with 5 days duration, and the Task Type is Fixed duration. I’ll do that Scenario in MS PROJECT 2013! … Continue reading
The Resume fields in MS PROJECT 2013
Hi, Imagine this situation: you have a Task with one Resource, and duration is 5 days. The task is on Track, and it is 50% completed. Suddenly, Resource get sick, and will be able to continue with work after few … Continue reading
% Complete vs. Finish Date in MS PROJECT 2013
Hi, here is another problem from one of my Blog readers: “Hi Nenad – allow me to give you an example of my problem. A task with a finish date of May 5/14 has a % complete of 25%. When … Continue reading
Adding new Resource on the Partial Finished Task in MS PROJECT 2013 – Part 2 of 2!
Hi, Today I’ll show another way of adding Resource after it is, for example, 40% Finished. first, I’ll show you pictures from my Previous Post, so I will create on simple Project in MS PROJECT 2013: and I will create … Continue reading
Adding new Resource on the Partial Finished Task in MS PROJECT 2013 – Part 1 of 2!
Hi, I had a very good question from one of my Blog Readers: “Hi Nenad. Can you tell me what is going to happen if I have one Resource on the Task, and that Task is finished, for example, 40%, … Continue reading
24 Hours Calendar – how it works in MS PROJECT 2013
Hi, I have a lot of questions about MS PROJECT 2013 Calendars, especially about 24 hours Calendar. I will explain how does it work in MS PROJECT 2013. First I will Create a very Simple Project with only one Task … Continue reading
Material Resources and Calendars in MS PROJECT 2013 – where is the link?
Hi, as usual, I have a question from one of my Blog Readers: “Hi Nenad. i follow your blog step but i added resource as material not as work, but it doesn’t come up to me in the calendars list … Continue reading