Replacing Generic Resources with Human Resources and overallocation!
Hi, I’ve got a question from one of my Blog readers: “When I assign Generic Resource to a Task and then replace it with human resource how can I decrease availability of generic Resource?” I will show you that in … Continue reading
“Keep task on nearest working day when changing to automatically scheduled mode” option in MS PROJECT 2016
Hi, a lot of my Blog readers asked me about “keep task on nearest working day when changing to automatically scheduled mode” option in MS PROJECT! I will show you what is it, and how does it work in MS … Continue reading
Extended duration when Successor has been started in MS PROJECT 2016
Hi, my Blog reader has a problem: “So what if we aren’t moving the project, just adding time to a task where a dependent task was able to start early. As an exampleTask A 10 daysTask B 2 daysTask C … Continue reading
Material Resources with new Resource assigned to the Tasks in MS PROJECT 2016
Hi, today I’m going to show you what is going to happen with Material resources when you assign additional Work resources to the Task which has already started and have some actuals. I will use Microsoft Project 2016! First I’m … Continue reading
Baseline and deleted Tasks in MS PROJECT 2013, what if I do not have Inactive button?
Hi, my last Blog post is here: https://ntrajkovski.com/2015/09/22/baseline-and-deleted-tasks-in-ms-project-2013/ But, I have a question about that. That question is: “Hi Nenad, do all versions of project have the deactivate function? If not, is there a workaround? “ The answer is, older … Continue reading
Baseline and deleted Tasks in MS PROJECT 2013
Hi, I got a lot of questions about differences, for example, in Task Table when Project has Baseline, and The Task is deleted. I will show you what do in MS PROJECT 2013! First, I will crate very Simple Project: … Continue reading
Baseline and Calendars in MS PROJECT 2013
Hi, I got a question from my Blog Reader: “Dear Nenad, I have a problem. I set up Base Calendar with exceptions. I create a Schedule, assign Resources, and I save the Baseline. But after some time I notice that … Continue reading
Overallocated fields in MS PROJECT 2013
Hi, today I will explain Overallocated fields in MS PROJECT 2013, because they are confusing a lot of my Blog readers. First I will create Project with three Tasks, and I will add Overallocated field in Gantt Chart View: I … Continue reading
Effort estimate in hours with MS PROJECT 2013
Hi, I’ve got a lot of questions like this one: “Hi, you have a lot of examples with estimating Durations! But we are estimate in hours. We don’t know Duration, but how many hours are needed to complete our Tasks! … Continue reading
Finish to Finish / Start to Start Dependencies with LAG in MS PROJECT 2013!
Hi, my Blog reader has a question: “Dear Nenad, can you explain Lag with Dependencies other than Finish to Start, like Finish to Finish and Start to Start?” I will show you how to do that in MS PROJECT 2013! … Continue reading