%Complete, %Work Complete, and Project without Resources with MS PROJECT 2016!
Hi, I’ve got a question from one of my Blog Readers: “Please clarify the following: I have created a Sample project in MS Project 2013, with tasks and assigned duration with required predecessors.I have base lined the plan and started … Continue reading
New Tasks and saved Baseline in MS PRIOJECT 2016
Hi, I have a reader who is novice in MS PROJECT 2016, and he has a problem; “Hi, I hope you are in good health. I have some quires about cost tracking in MS Project. I had previously saved … Continue reading
Effect of initial resource assignment on calculation of Individual resource’s work in MS PROJECT 2016
Hi, I’ve got very good question form one of my Blog readers: “The effect of initial resource assignment on calculation of Individual resource’s work. Suppose we want have two resources R1 (100%) and R2(50%) to work on a 20h fixed … Continue reading
How to setup complex Graphical Indicators with MS PROJECT 2016
Hi, I can see on the forums that lot of MS PROJECT 2016 user have problem with graphical indicators. For example, they want to see Actual Work compared with base lined work, and see the status. OK, that is not … Continue reading
How to change Resource Assignments for Multiple Tasks in MS PROJECT 2016
Hi, Here is a problem that one of my Blog Readers have: “Is there a way to have the same resource – Team A work on multiple tasks and a place where I can change the “Units %” from 300% … Continue reading
Duration vs. Manually entered actual work in MS PROJECT 2016
Hi, I’ve got a question form one of my Blog readers: “Hi Nenad,Based on the example in your previous post please answer the following questions:1) When you manually updated the actual work in each of the 3 days for Resource … Continue reading
Actual Duration vs. Actual work in MS PROJECT 2016
Hi, I got a Business Case from my Blog Reader wit, of course, a problem. I will go step by step through it with MS PROJECT 2016! In Italic font is my blog reader Text 1. I created a … Continue reading
Resource Calendar vs. Units in Microsoft Project 2016
Hi, I’ve got a very good question from one of my blog Readers: “Dear Nenad, Could you please help me with a question on resource calendar?If a resource is part time only work 3 days a week. I need to … Continue reading
How to change rates and costs without affecting past Tasks in MS PROJECT 2016?
Hi, I’ve got a question from one of my Blog Readers: “Hi!I am wondering how you would manage a rate increase in MS Project halfway through the project that is not retroactive. If I change the $/hr for a resource, … Continue reading
% Complete and Actual hours for particular Resource in MS PROJECT 2016
Hi, I got interesting question from one of my Blog Readers: “Nenad this is very helpful, however, how would you adjust the scenario where the Actual work by John (100%) and Tom (50%) who are two resources assigned to this … Continue reading