How to put different Overtime Work to Task in MS PROJECT 2016!

Hi, I have a very interesting question from one of my Blog Readers: “Hi Nenad, I want to put different overtime Work for a Task and Resources. Let’s say that I have Task1, and John an Mary are assigned to … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 1 Comment

%Complete, %Work Complete, and Project without Resources with MS PROJECT 2016!

Hi, I’ve got a question from one of my Blog Readers: “Please clarify the following: I have created a Sample project in MS Project 2013, with tasks and assigned duration  with required predecessors.I have base lined the plan and started … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , , | Leave a comment

New Tasks and saved Baseline in MS PRIOJECT 2016

  Hi, I have a reader who is novice in MS PROJECT 2016, and he has a problem; “Hi, I hope you are in good health. I have some quires about cost tracking in MS Project. I had previously saved … Continue reading

Posted in Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | 1 Comment

Resource capacity in Hours with MS PROJECT 2016 – is it possible?

Hi, my Blog Reader has a question: “I have a project plan with certain milestones which are to be completed on specific dates and I have resources assigned. But as per plan, the resource allocation hours are reduced whereas in … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Actual Duration, Actual work and Fixed work Tasks in MS PROJECT 2016

Hi, here is one problem that my Blog Reader has (I will go step by step, and I will use MS PROJECT 2016) “When multiple resources are assigned to the task, for a given Total Work we can  calculates the   … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , | 1 Comment

Effect of initial resource assignment on calculation of Individual resource’s work in MS PROJECT 2016

Hi, I’ve got very good question form one of my Blog readers: “The effect  of initial resource assignment on  calculation  of  Individual resource’s work. Suppose we want have two resources R1 (100%) and R2(50%) to work on a 20h fixed … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | 4 Comments

A question for my Blog readers!

Hi, I got a suggestion, and I want to hear what do you think about it: “Have you considered doing videos instead of screenshots, it would be easier for us to understand and I guess you would save time.” I … Continue reading

Posted in MS PROJECT 2016 | Tagged | 15 Comments

Relation between Overtime and Duration in MS PROJECT 2016

Hi, I have a question from oen of my Blog readers: “Every time I allocate the whole work hours to overtime hours the Duration column turns into 0 and the start and finish dates and time are the same. Why?” … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

How to setup complex Graphical Indicators with MS PROJECT 2016

Hi, I can see on the forums that lot of MS PROJECT 2016 user have problem with graphical indicators. For example, they want to see Actual Work compared with base lined work, and see the status. OK, that is not … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , | 1 Comment

How to change Resource Assignments for Multiple Tasks in MS PROJECT 2016

Hi, Here is a problem that one of my Blog Readers have: “Is there a way to have the same resource – Team A work on multiple tasks and a place where I can change the “Units %” from 300% … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 3 Comments