-
Recent Posts
Archives
Categories
Category Archives: PRoject Management
Is it Possible to prevent assigning Resource to Task in MS PROJECT 2013?
Hi, again a question form my Blog reader: “Is it possible to disable assigning Resource to the Task, and still keep same resource in Resource sheet?” Let me show you in MS PROJECT 2013 First I’ll create Brand new Project … Continue reading
Multiple Resource Pools in Subprojects in MS PROJECT 2013!
Hi, I have a question from on of my Blog Readers: “Is it possible to use separate Resource to Projects, and then to see all Resources in one Master Project?” The answer is: “YES” How? I’ll show you in MS … Continue reading
Bug with Inactive Tasks in MS PROJECT 2013!
Hi, My MVP Fellow, Dale Howard found this Bug in MS PROJECT 2013! I will Create brand new Project with some Tasks: Now, suppose that I want to make First four Tasks inactive: I will get: So far so good. … Continue reading
Bug in Tracking Gantt View in MS PROJECT 2013
Hi, here is another small bug in MS PROJECT 2013. I will Create few Tasks in MS PROJECT 2013: I want to see Critical Path, so I’m going to Use Tracking Gantt View: and I’ll get: On the Right side … Continue reading
BUG Resource-related Cost field not recalculated in MS PROJECT 2013
Hi, here is minor bug in MS PROJECT 2013, found by Eric Uyttewaal, my MVP friend. First I am going to create New Project with Single Task (1 day duration): I will now Create two Resources: Ted and Fred: Yu … Continue reading
How to replace Resource for the partial completed Tasks in MS PROJECT 2013?
Hi, I’ve got a question from one of my Blog Readers: “Dear Nenad, I have the following scenario: I have A Task assigned with one Resource. He did 50% work, and then he left the Company. I must assign another … Continue reading
The Resume fields in MS PROJECT 2013
Hi, Imagine this situation: you have a Task with one Resource, and duration is 5 days. The task is on Track, and it is 50% completed. Suddenly, Resource get sick, and will be able to continue with work after few … Continue reading
% Complete vs. Finish Date in MS PROJECT 2013
Hi, here is another problem from one of my Blog readers: “Hi Nenad – allow me to give you an example of my problem. A task with a finish date of May 5/14 has a % complete of 25%. When … Continue reading
Resources and Durations – how are they linked in MS PROJECT 2013!
Hi, very good friend of mine has a problem: “Nenad, please help me. I want to have some Resources with different working hours (for Example, John 1 hour per day, Mary 2 hours per day), and when I assign Single … Continue reading
Strange Duration in MS PROJECT 2013 – Bug or Not!
Hi, I will show you something that makes MS PROJECT users crazy! Of course I’ll use MS PROJECT 2013. I will first, create a Brand new Project with one Task with 5 days Duration, like this: Everything is just fine. … Continue reading