Tag Archives: Microsoft Project 2010
Recurring week exceptions in MS PROJECT 2013
Hi, Suppose that you are working on the Project! And suppose that you have one week Vacation for whole company resources, each and every Year. How to make it in MS PROJECT 2013. First I’ll create a Project With one … Continue reading
% Complete vs % Work Complete in MS PROJECT 2013
Hi, some people asked me about difference between %Complete, and %Work Complete. I’ll show you the difference with a very simple example in MS PROJECT 2013. First, I will create a Simple Project with a single Task: I will have … Continue reading
ASAP and ALAP constraint combination in MS PROJECT 2013
Hi, my Blog Reader has a problem: “Please can you help me. I would like to know how I can ask MS project to set one task ALAP without causing successors to move ALAP as well. In other words, I … Continue reading
Tracking resources exact hours on a standard calendar in MS PROJECT 2013
Hi, Again a question from one of my Blog readers: “Dear Nenad,I really appreciate your blog…helps me immensely.I would really be grateful if you could help me on tracking resources exact hours on a standard calendar. I am interested … Continue reading
How to apply multiple Resource Calendars to the Same Resource in MS PROJECT 2013?
Hi, my Blog reader has a problem: “My problem is that some of resources have 2 work schedules. When they work on-shore (5 days week 8 hours day) and off-shore (7 days week and 11 hours day), For each … Continue reading
Baseline for Subprojects in MS PROJECT 2013
Hi, Today I’m going to explain how to set and see Baseline for Subprojects in MS PROJECT 2013, and how to see those Baselines in Master Project! First I’m going to create two Brand new Projects with one Task: and … Continue reading
How to Assign different Overtime Rate in MS PROJECT 2013
Hi, in one of my Posts I have explained how to calculate and work with Overtime hours in MS Project 2013, so I am not going to do it again. This time I will explain how to apply different … Continue reading
How to replace Generic resources with those with specific skills in MS PROJECT 2013
Hi, again my Blog Reade has a Problem. Here it is: “I have a challenging task to transition unorganized planning in my company to using ms project professional 2010 with share point site. We have generic resources like developers, testers … Continue reading
Work without Resources in MS PROJECT 2013! Is it possible?
Hi, again I have a question from my Blog Reader: “Can you advise me how to handle a closed task that has a resource assigned, but the resource will eventually spend 0 hours. So it is in fact a 100 … Continue reading
How to manage Projects with SharePoint 2013 and MS PROJECT Professional 2013 – Part 2
Hi! Here is Scenario! I want to Manage my Project in MS PROJECT PRO 2013! I want to upload an mpp file in SharePoint 2013, and there I want to have all my Project Documents, and I want to track … Continue reading