Category Archives: Microsoft Project 2013
Start and Finish Date with Auto Scheduled Task
Hi, first of all, apologies for delaying with my regular Post, but I was very busy with organizing SPCAdriatics (SharePoint and Project) conference last weeks (www.spcadriatics.com) Again, a question from one of my Blog readers: “Greetings Sir, Thanks kindly for … Continue reading
Lag in MS PROJECT 2013
Hi, these days I’m busy with organizing Conference (www.spcadriatics.com), btu I have a question form on of my Blog Readers, so I do not want to disappoint him. Here is the question: “This is very good information thank you. I … Continue reading
Recurring week exceptions in MS PROJECT 2013
Hi, Suppose that you are working on the Project! And suppose that you have one week Vacation for whole company resources, each and every Year. How to make it in MS PROJECT 2013. First I’ll create a Project With one … Continue reading
% Complete VS Physical % Complete in MS PROJECT 2013
Hi, I will explain hot to track Physical % Complete in MS PROJECT 2013. In MS PROJECT you can Track %Complete, % Work Complete, and Physical % Complete. Where are the differences? % Complete is about Duration % Work Complete … Continue reading
% Complete vs % Work Complete in MS PROJECT 2013
Hi, some people asked me about difference between %Complete, and %Work Complete. I’ll show you the difference with a very simple example in MS PROJECT 2013. First, I will create a Simple Project with a single Task: I will have … Continue reading
Percentage completed vs. Actual Work in MS PROJECT 2013!
Hi, again, my Blog reader has a problem: “Dear Nenad, your blog is a real treasure and I am so happy I came across it a year ago when we started with the implementation of the MS Project Server 2010 … Continue reading
ASAP and ALAP constraint combination in MS PROJECT 2013
Hi, my Blog Reader has a problem: “Please can you help me. I would like to know how I can ask MS project to set one task ALAP without causing successors to move ALAP as well. In other words, I … Continue reading
Tracking resources exact hours on a standard calendar in MS PROJECT 2013
Hi, Again a question from one of my Blog readers: “Dear Nenad,I really appreciate your blog…helps me immensely.I would really be grateful if you could help me on tracking resources exact hours on a standard calendar. I am interested … Continue reading
How to apply multiple Resource Calendars to the Same Resource in MS PROJECT 2013?
Hi, my Blog reader has a problem: “My problem is that some of resources have 2 work schedules. When they work on-shore (5 days week 8 hours day) and off-shore (7 days week and 11 hours day), For each … Continue reading
Baseline for Subprojects in MS PROJECT 2013
Hi, Today I’m going to explain how to set and see Baseline for Subprojects in MS PROJECT 2013, and how to see those Baselines in Master Project! First I’m going to create two Brand new Projects with one Task: and … Continue reading