Collapsing the Ribbon in MS PROJECT 2013

Hi, this will be an easy one, because tomorrow is a New Year (2014), so I’ll finish this year with an answer to my Blog Reader. The Problem is very Simple: “Dear Sir, I’m using the Ribbon all the time, … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 2 Comments

Work Package versus Activity in MS PROJECT 2013

  Hi, another question from one of my Blog Readers: “Hello; I have a question about “work package”. Is work package the same as “activity” or “activity” is more detailed than a work package? Thank you” Theory first. Suppose that … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 4 Comments

Generic Resources and different capacity in MS PROJECT 2013

Hi, again one interest question from my Blog reader: “Dear Nenad,Thank you VERY much for your very informative blog! I enjoy reading your posts and visit the site often. I would appreciate if you could answer my question regarding managing … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 4 Comments

Scheduling Problem in MS PROJECT 2013

Hi, again a question from one of My Blog Readers: “What if you work 9 hrs per day mon to thurs and 8 hrs per day friday for week 1, and for week 2 you work 9 hrs per day … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft SharePoint, PMI | Tagged , , , , , | 2 Comments

Start and Finish Date with Auto Scheduled Task

Hi, first of all, apologies for delaying with my regular Post, but I was very busy with organizing SPCAdriatics (SharePoint and Project) conference last weeks (www.spcadriatics.com) Again, a question from one of my Blog readers: “Greetings Sir, Thanks kindly for … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 3 Comments

Lag in MS PROJECT 2013

Hi, these days I’m busy with organizing Conference (www.spcadriatics.com), btu I have a question form on of my Blog Readers, so I do not want to disappoint him. Here is the question: “This is very good information thank you. I … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft Project 2013, PMI | Tagged , , , , , | Leave a comment

Recurring week exceptions in MS PROJECT 2013

Hi, Suppose that you are working on the Project! And suppose that you have one week Vacation for whole company resources, each and every Year. How to make it in MS PROJECT 2013. First I’ll create a Project With one … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project 2013 - Preview, Microsoft Project Server 2010, PMI | Tagged , , , , , | 3 Comments

% Complete VS Physical % Complete in MS PROJECT 2013

Hi, I will explain hot to track Physical % Complete in MS PROJECT 2013. In MS PROJECT you can Track %Complete, % Work Complete, and Physical % Complete. Where are the differences? % Complete is about Duration % Work Complete … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 10 Comments

% Complete vs % Work Complete in MS PROJECT 2013

Hi, some people asked me about difference between %Complete, and %Work Complete. I’ll show you the difference with a very simple example in MS PROJECT 2013. First, I will create a Simple Project with a single Task: I will have … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 13 Comments

Percentage completed vs. Actual Work in MS PROJECT 2013!

Hi, again, my Blog reader has a problem: “Dear Nenad, your blog is a real treasure and I am so happy I came across it a year ago when we started with the implementation of the MS Project Server 2010 … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 9 Comments