Work Package versus Activity in MS PROJECT 2013

  Hi, another question from one of my Blog Readers: “Hello; I have a question about “work package”. Is work package the same as “activity” or “activity” is more detailed than a work package? Thank you” Theory first. Suppose that … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 4 Comments

Generic Resources and different capacity in MS PROJECT 2013

Hi, again one interest question from my Blog reader: “Dear Nenad,Thank you VERY much for your very informative blog! I enjoy reading your posts and visit the site often. I would appreciate if you could answer my question regarding managing … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 4 Comments

Scheduling Problem in MS PROJECT 2013

Hi, again a question from one of My Blog Readers: “What if you work 9 hrs per day mon to thurs and 8 hrs per day friday for week 1, and for week 2 you work 9 hrs per day … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft SharePoint, PMI | Tagged , , , , , | 2 Comments

Start and Finish Date with Auto Scheduled Task

Hi, first of all, apologies for delaying with my regular Post, but I was very busy with organizing SPCAdriatics (SharePoint and Project) conference last weeks (www.spcadriatics.com) Again, a question from one of my Blog readers: “Greetings Sir, Thanks kindly for … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 3 Comments

Recurring week exceptions in MS PROJECT 2013

Hi, Suppose that you are working on the Project! And suppose that you have one week Vacation for whole company resources, each and every Year. How to make it in MS PROJECT 2013. First I’ll create a Project With one … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project 2013 - Preview, Microsoft Project Server 2010, PMI | Tagged , , , , , | 3 Comments

% Complete VS Physical % Complete in MS PROJECT 2013

Hi, I will explain hot to track Physical % Complete in MS PROJECT 2013. In MS PROJECT you can Track %Complete, % Work Complete, and Physical % Complete. Where are the differences? % Complete is about Duration % Work Complete … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 10 Comments

% Complete vs % Work Complete in MS PROJECT 2013

Hi, some people asked me about difference between %Complete, and %Work Complete. I’ll show you the difference with a very simple example in MS PROJECT 2013. First, I will create a Simple Project with a single Task: I will have … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 13 Comments

Percentage completed vs. Actual Work in MS PROJECT 2013!

Hi, again, my Blog reader has a problem: “Dear Nenad, your blog is a real treasure and I am so happy I came across it a year ago when we started with the implementation of the MS Project Server 2010 … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 9 Comments

ASAP and ALAP constraint combination in MS PROJECT 2013

Hi, my Blog Reader has a problem: “Please can you help me. I would like to know how I can ask MS project to set one task ALAP without causing successors to move ALAP as well. In other words, I … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PRoject Management | Tagged , , | Leave a comment

Tracking resources exact hours on a standard calendar in MS PROJECT 2013

  Hi, Again a question from one of my Blog readers: “Dear Nenad,I really appreciate your blog…helps me immensely.I would really be grateful if you could help me on tracking resources exact hours on a standard calendar. I am interested … Continue reading →

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI | Tagged , , , , | Leave a comment